Project Name Cross Power
LIHI Certificate No. 174
LIHI Certificate Term August 31, 2026 – August 30, 2036
Owner Great Lakes Hydro America, LLC, a subsidiary of Brookfield Renewable Energy Group
State New Hampshire
Location River Mile 136.9 – Androscoggin River
Installed Capacity 3.445 MW
Average Annual Generation 12,674 MWh
Facility Type Run of river
FERC No. P-2326, issued in 2025, expires 08/31/2065

The Cross Power Project is located on the Androscoggin River in Coos County, northern New Hampshire. The Androscoggin River is runs through the states of New Hampshire and Maine. The river joins the Kennebec River at Merrymeeting Bay in Maine before emptying into the Gulf of Maine and subsequently the Atlantic Ocean. The Androscoggin River watershed contains 19 hydroelectric projects located along the 178-mile-long river.

The Project is one of several hydroelectric projects within an 11-mile reach of the Androscoggin River between Berlin and Shelburne, New Hampshire, including the upstream Sawmill Project (LIHI #173) and downstream projects: Cascade (LIHI #188), Upper Gorham (LIHI #175), Gorham (LIHI #153), and Shelburne (LIHI #176).

The Cross Power dam was originally constructed in 1903.  It is 448 feet long with a maximum height of 20 feet and is comprised of:

  • Concrete non-overflow sections adjoined to a ledge outcropping. One section contains a stop-log opening used to pass accumulated debris. The other section is located from the outcropping to the spillway.
  • A 276-foot-long spillway section with newly designed 42-inch-high flashboards installed in the fall of 2020.
  • A gatehouse 19 feet wide by 124 feet long with five bays. Each bay contains trashracks 21.6 feet wide by 18.4 feet-high with 3-inch clear spacing.
  • A concrete retaining wall extending from the gatehouse to the river embankment.

The powerhouse is located 44 feet downstream of the gatehouse. The powerhouse is a concrete substructure with brick superstructure with an addition on the downstream shore side containing five horizontal propeller turbines with a total installed capacity of 3.445 MW.

The project operates in quasi-run-of-river mode and impounds a 22-acre reservoir. The impoundment is allowed to fluctuate over a 6-inch range. Since the bypass reach is very short, the powerhouse is essentially integral to the dam, and due to backwatering from the downstream Cascade Project, no minimum flow release is specified. The flow regime was developed in consultation with US Fish and Wildlife Service (USFWS) and the New Hampshire Department of Environmental Services.

Waters within the project reach are designated Class B, suitable for fishing, primary contact recreation, and water supply after treatment. The project waters are listed as impaired for prior discharges from several paper mills. Given run-of-river operations, the project is unlikely to adversely impact water quality.

The Androscoggin River is not accessible to diadromous fish species in the project reach due to downstream natural falls – Lewiston and Rumford Falls. American eel are present in the lower reaches of the Androscoggin River though none have historically reached the upper sections of the river. The project area supports cold-water fishery habitat. New Hampshire Department of Fish and Game annually stocks brook, rainbow, and brown trout upstream of the project. Resident river species include fallfish, smallmouth bass, white sucker, longnose dace, common shiner, spottail shiner, and yellow perch. Downstream passage can occur by means of spillway flow, low-level gate releases, and power intake flow through the trashracks. The project does not impede the successful completion of resident fish life cycles.

The project lands are limited to the area occupied by project infrastructure. The project’s run-of-river operations and limited impoundment fluctuation provides protection for shoreline areas.

Threatened or endangered species potentially present in the project vicinity include the Northern long-eared bat, Canada lynx, the proposed for listing tri-colored bat and monarch butterfly. The project avoids removing trees from April 15 through October 31, unless emergency tree removal for public safety is necessary.

The project’s dam, powerhouse, gatehouse, and gatehouse machinery are eligible for listing on the National Register of Historic Places (NRHP). No Native American lands, known as traditional cultural properties, or NRHP-eligible tribal resources are present within the Project boundary. The project operates under a Programmatic Agreement (PA) in consultation with the State Historic Preservation Office. The PA and related Historic Properties Management Plan (HPMP) provides provisions detailing annual monitoring and reporting concerning repair and improvement activities conducted as well as any scheduled activities for the upcoming year.

Recreational resources at the project include a tailrace fishing area and non-project Glenside Park. The project is required to develop a Recreation Management Plan (RMP) within one year of license issuance to address the identified lack of impoundment access and to formalize recreational features. Public access is provided free of charge.


Compliance Status

The Certificate includes the following facility-specific conditions:

Condition 1: The Facility Owner shall submit the final Operational Compliance Monitoring Plan (OCMP) to LIHI once it has been approved by resource agencies and FERC. In annual compliance submittals to LIHI the Facility Owner shall submit a summary of all planned and unplanned operational deviations that occurred during the year along with evidence of resource agency consultation and comments received.

Condition 2: The Facility Owner shall submit the final Historic Properties Management Plan (HPMP) to LIHI once it has been approved by the SHPO and FERC. In annual compliance submittals to LIHI, the Facility Owner shall report on any consultation that occurred during the year related to ground-disturbing or other activities subject to the HPMP.

Condition 3: The Facility Owner shall submit the Recreation Management Plan (RMP) to LIHI once it has been approved by resource agencies and FERC. In annual compliance submittals to LIHI, the Facility Owner shall report on any required maintenance, development of sites or other activities subject to the RMP.

2026: Annual reporting for the current Certificate has not yet taken effect.


Certification History

August 18, 2026: The Low Impact Hydropower Institute has preliminarily approved Low Impact recertification for the Cross Power Hydroelectric Project. The mid-term review applications and reviewer report are available below. The certification includes three conditions included in the review report to ensure that FERC relicensing implementation measures are timely met. The decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Cross Power Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 68 Harrison Ave Ste 605, PMB 113938 Boston, Massachusetts 02111-1929. All requests will be posted to the website. The applicant will have an opportunity to respond, and any response will also be posted. Requests must be received by 5 pm Eastern time on September 17, 2026. If no appeal requests are received the new certification term will be August 31, 2026 through August 30, 2036.

April 28, 2026: The Low Impact Hydropower Institute has received a complete application (see below)  for a mid-term review of the Cross Power Project. The Project is one of several LIHI Certified projects located on the upper Androscoggin River in New Hampshire that were issued new FERC licenses in September 2025. In accordance with Section 5.3.4 of the 2nd Edition LIHI Handbook, issuance of a new license constitutes a “material change” and triggers a mid-term LIHI Certification review.

 LIHI is seeking public comment on this application. Specifically, we are interested in knowing whether you think the Project continues to meet the LIHI Low Impact Certification Criteria, as revised in the 2nd Edition Handbook. Comments that are directly tied to specific LIHI criteria (flows, water quality, fish passage, etc.) will be most helpful, but all comments will be considered. Comments may be submitted to LIHI by e-mail at comments@lowimpacthydro.org with “Cross Power Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 68 Harrison Ave. Ste 605, PMB 113938, Boston MA 02111-1929. Comments must be received by 5 pm Eastern time on June 27, 2026 to be considered. All comments will be posted to the website, and the applicants will have an opportunity to respond. Any response will also be posted.

January 1, 2022: The LIHI Certificate term has been extended in accordance with Revision 2.05 of the LIHI 2nd Edition Certification Handbook issued January 1, 2022. Refer to the facility table above for the new term.

November 30, 2020: The decision to certify the Cross Power Project became final after the close of the appeals period on November 27, 2020 with no appeals filed. The Certification term is from August 31, 2020 – August 30, 2025.

October 27, 2020:The Low Impact Hydropower Institute (LIHI) preliminarily approved Low Impact Certification for the Sawmill, Cross Power, Upper Gorham, and Shelburne Hydroelectric Projects located on the Androscoggin River in New Hampshire. This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests for one or more of these projects can be submitted by email to comments@lowimpacthydro.org with “Androscoggin River-NH Projects” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on November 27, 2020.The full application and review report are available below. If no appeal requests are received the certification term for each project will be August 31, 2020 through August 30, 2025.

August 13, 2020: The Low Impact Hydropower Institute has received a complete application for Low Impact Certification of the Sawmill, Cross Power, Upper Gorham and Shelburne Hydroelectric Projects located on the Androscoggin River in New Hampshire. LIHI is seeking public comment on this application. Specifically, we are interested in knowing whether you think the Projects meet the LIHI Low Impact Certification Criteria, as revised in the 2nd Edition Handbook. The application can be found below. Comments that are directly tied to specific LIHI criteria (flows, water quality, fish passage, etc.) will be most helpful, but all comments will be considered. Comments may be submitted to the Institute by e-mail at comments@lowimpacthydro.org with “Androscoggin River-NH Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420. Comments must be received on or before 5 pm Eastern time on October 12, 2020 to be considered. All comments will be posted to the web site and the applicant will have an opportunity to respond. Any response will also be posted.


Certification Files

2026 Mid-Term Review

2020 Certification