Proposal – New Recertification Process
October 28, 2020West Branch St. Regis Project, LIHI #27 – Complete Application Received
October 30, 2020Lexington MA (October 30, 2020): The Low Impact Hydropower Institute (LIHI) has preliminarily approved recertification of the Crocker Dam Project (LIHI #127) for a new 5-year term of Low Impact Certification. The Project is located on the Whitman River in Massachusetts.
This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Crocker Dam Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on November 29, 2020. The full application and reviewer’s report are available HERE.
If no appeal requests are received and the decision becomes final, the Certification term for the Project will be September 15, 2020 through September 14, 2025.
Preliminary Decision – Certification of the Wells Dam Project, pending LIHI #203, WA
Read more