LIHI Certificate #40 - Vernon Project, New Hampshire/Vermont

Project Name Vernon
LIHI Certificate No. 40
LIHI Certificate Term December 15, 2013
December 15, 2018, extended to December 31, 2024
Owner Great River Hydro, LLC
State New Hampshire, Vermont
Location Located at river mile 142 on the Connecticut River, in Cheshire County, New Hampshire and Windham County, Vermont.
Installed Capacity 32.4 MW
Average Annual Generation 162,557 MWh (2008-2016)
Facility Type Daily cycling
FERC No. P-1904 issued in 1979, expired 2019 – in relicensing

The Vernon Project is located on the Connecticut River in Cheshire County, New Hampshire and Windham County, Vermont. The project was originally built in 1909 and included the dam, powerhouse, and eight turbine units. A powerhouse extension was completed in 1926, bringing two more turbine units online. Other major upgrades throughout the years include the completion of an upstream fish ladder in 1981, construction of downstream fish passage facilities in 1995, and the replacement of turbine Units Nos. 5-8 in 2008.

The closest dam is Turner’s Falls dam about 20 miles downstream in Massachusetts. The Turner’s Falls impoundment backwaters to the base of Vernon dam and also forms the lower reservoir for the Northfield Mountain Pump Storage Project. The nearest upstream dams are the Bellows Falls Project about 32 miles away and the Wilder Project, another 44 miles upstream.

The dam is a composite overflow and non-overflow ogee-type, concrete gravity structure extending across the Connecticut River between Hinsdale, New Hampshire, and Vernon, Vermont. The dam is 956 feet long with a maximum height of 58 feet. It includes the integral powerhouse with a sluice gate block section that is about 356 feet long and a concrete overflow spillway section about 600 feet long. The spillway portion of the dam is divided into 12 bays containing a trash/ice sluice, 4 Tainter gates, 2 hydraulic flashboard bays, 3 stanchion bays, and 2 more Tainter gates. The various bays are separated by concrete piers supporting a steel and concrete bridge that runs the length of the dam for access and for operation of flashboards. The trash/ice sluice is a skimmer gate that passes logs and other debris deflected away from the powerhouse by a log and ice boom in the powerhouse forebay. The powerhouse contains ten turbine generating units. Units 1-4 and 9-10 are single runner vertical Francis units while Units 5-8 are vertical axial flow Kaplan units. Total installed capacity is 32.4 MW.

The project operates in a daily cycling mode with limited storage, impounding a 2,550-acre reservoir. There is no bypassed reach. The project provides a minimum flow of at least 1,250 cfs. This flow regime was developed based on recommendations from the US Department of the Interior and supported by the US Environmental Protection Agency to prevent heat build-up in the reservoir from cooling system discharges from the Vermont Yankee Nuclear Power Plant, decommissioned in 2014.

Waters within the project reach are designated as impaired for pH and mercury in fish tissue caused by atmospheric deposition. Recent water quality studies demonstrate that the project meets state water quality standards.

The project includes an upstream fish ladder designed to pass Atlantic salmon and American shad which became operational in 1981. The ladder design includes two types of fishway: an ice harbor pool-and-weir design at the lower end and a serpentine vertical-slot design at the upper end. Between the two, a reregulating bay is used to adjust the volume of water moving between the upper and lower sections. This bay also includes a fish trap mechanism and counting window. The facility also supports passage for sea lamprey, American eel, and some resident species (bass, sucker, walleye, trout, and sunfish). Permanent downstream passage facilities were constructed in 1995 that consists of a “fish pipe” that discharges about 350 cfs through the powerhouse, a second smaller “fish bypass” at the Vermont end of the powerhouse that discharges about 40 cfs, and a 156-foot-long louver array that extends from the forebay to the fish pipe entrance. The louver intercepts and directs downstream-migrating fish that enter the forebay from midriver and from the east (New Hampshire) shoreline into the fish pipe. The smaller fish bypass on the Vermont end of the powerhouse functions as a secondary passage route for fish that are not intercepted by the louver array.

The project lands consist of the areas surrounding the project facilities as well as 287 acres of fee-owned land, with 223 acres set aside as undeveloped. Most of the shoreline is privately owned and is not under project ownership.

Threatened or endangered species potentially present in the project vicinity include Northern long-eared bat, bald eagle, cobblestone tiger beetle, Fowler’s toad and pygmy weed. Bald eagles have been observed in the project area in New Hampshire and likely use the project downstream reaches of the river as foraging habitat, especially during the winter as the flow from the project prevents the water from icing over. Pygmy weed is a freshwater tidal species which was newly discovered in the project area in 2012. The daily fluctuations due to project operations account for the species presence in the river. Cobblestone tiger beetle was found at the far upper extent of the 26-mile-long impoundment and unlikely to be impacted by project operations. Fowler’s toad is found downstream of the dam. Recent studies suggest that project operations may be providing safe habitat for the pygmy weed and Fowler’s toad.

The buildings and structures associated with the project are eligible for listing on the National Register of Historic Places as its own Historic District. The New Hampshire State Historic Preservation Office has concluded that project operations do not adversely impact the historic resources at the project.

Recreational resources at the project include a picnic area, boat launch, swimming area, canoe portage, and boat-in camp sites. Maps, recreation facility descriptions and flow forecasts can be found HERE. Public access is provided free of charge.


Compliance Status

The Certificate includes the following facility-specific conditions:

  • Condition 1: The facility must provide effective upstream and downstream fish passage and protection for migratory fish species.  Therefore, the Owner shall continue consultation with the USFWS, VANR, VFWD and NHFG to identify appropriate measures to pass juvenile shad downstream, as well as for any other migratory species that the agencies deem appropriate. If any agency recommends that improvements are needed to achieve satisfactory downstream passage, the Owner shall provide to LIHI a copy of those recommendations, along with the Owner’s position on those improvements as soon as is practicable.  No later than December 31, 2016, and annually after that date, the Owner shall report to LIHI on the status of fish passage improvements and associated agency consultations.
  • Condition 2: The Owner shall proactively consult with the resource agencies regarding possible interim opportunities to enhance fish passage for American eel and riverine species while the FERC relicensing activities are underway. Such opportunities may involve study and design of fish passage mitigation measures for these species so that they can be implemented more quickly once a new license is issued. During the term of this new LIHI certification, should a resource agency request implementation of upstream or downstream passage measures for anadromous, catadromous, or riverine fish as part of their recommendations/mandates under the new licensing proceedings, the Owner shall notify LIHI within 30 days, provide LIHI with a copy of the request, and describe the Owner’s plan to address these requests.
  • Condition satisfied in 2017. Condition 3: The Owner shall develop a plan and schedule for repair and maintenance of the recreational facilities at the Governor Hunt Picnic Area, including the boat launch, trash collection, and sanitary facilities.  The Owner shall make best efforts to ensure these recreational facilities are well maintained. The recreation plan and schedule for its implementation shall be submitted to LIHI as soon as practicable, but no later than June 30, 2017.
  • Condition 4: The Owner will provide a concise letter report to LIHI annually, providing a status report on FERC licensing progress, listing significant agency interactions that have occurred in the past year that are relevant to LIHI’s certification criteria, and highlighting major topics of agreement or disagreement.  This report will be provided to LIHI as part of the owner’s annual compliance statement.  LIHI reserves the right to request additional details if necessary, if highlighted topics are relevant to LIHI’s certification criteria and their associated goals.
  • Condition 5: If the on-going FERC relicensing proceeding is concluded and a new Commission Order is issued for the facility during the term of the new LIHI certification, the Owner shall notify LIHI within 30 days of that action. Within 60 days of a new FERC license being issued, the owner shall provide LIHI with a report that identifies all material differences between the requirements of the new FERC license and the standards used to satisfy LIHI’s criteria or conditions on the new LIHI certificate. LIHI reserves the right to adjust any and all conditions on the LIHI certificate, pending the outcome of the FERC relicensing, to ensure consistency between the LIHI certificate and the new FERC license.  If the on-going relicensing proceeding is not concluded prior to the expiration of the term of the new LIHI certification, no action is required on this condition.
  • Condition 6: The Connecticut River basin is highly developed for water resources and the operation of multiple hydropower facilities and other water uses in the basin are interconnected to a degree that requires a systematic approach for future water management.  Solutions for individual facilities are insufficient to achieve the environmental protection and restoration needed for long-term, sustainable water uses.  Therefore, the owner of the Vernon facility shall continue to play a constructive, supportive role in promoting integrative water management in the basin, both in the ongoing FERC relicensing and in other regulatory proceedings that may develop in the basin.  The owner shall report to LIHI on its activities relative to this condition each year in its annual compliance report. LIHI reserves the right to modify the certificate conditions again if needed.

2022: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.  For Condition 1, the project reported execution of a fish passage settlement agreement with fishery agencies. For Condition 2, the project reported improvements to the fish ladder that allows for off-site real-time monitoring of attraction water volume, and entrance gate elevation. For Conditions 4 and 5, the project provided a relicensing status update, awaiting FERC’s issuance of Ready for Environmental Analysis.  For Condition 6, the project reported on ongoing watershed related activities.

2021: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported ongoing consultation on a fish passage plan and schedule . For Condition 2, the project reported completion of additional fish ladder modifications. For Conditions 4 and 5 the project reported on fish passage settlement negotiations and filing of additional recreation enhancement information with FERC.  For Condition 6, the project reported on ongoing watershed related activities.

2020: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported ongoing consultation. For Condition 2, the project reported completion of the 2019 eel passage relicensing study and planned additional fish ladder modifications. For Conditions 4 and 5 the project reported on stakeholder consultation regarding proposed operational changes and filing of the amended final license application on 12/07/2020.  For Condition 6, the project reported on ongoing watershed related activities.

2019: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported filing the last of the relicensing study reports and ongoing consultation. For Condition 2, the project reported on additional fish ladder modifications and a new eel passage relicensing study. For Conditions 4 and 5 the project reported on FERC process updates and additional stakeholder consultation.  For Condition 6, the project reported on watershed activities.

2018: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported ongoing consultation. For Condition 2, the project reported on fish ladder modifications. For Conditions 4 and 5 the project reported on additional relicensing studies, filing of study reports, and stakeholder consultation.  For Condition 6, the project reported on watershed activities.

2017: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported ongoing fish passage relicensing studies. For Condition 2, the project reported installation of a temporary eel trap. For Condition 3, the project reported completion of the recreation plan and schedule, thus satisfying the condition. For Conditions 4 and 5 the project reported filing its final FERC relicensing application on 05/01/2017 and filing of various study reports, fishway modifications, and ongoing consultation.  For Condition 6, the project reported on watershed activities.

2016: There were no reported changes or compliance issues.  The project remains in compliance based on the annual review.  For Condition 1, the project reported ongoing fish passage relicensing studies. For Condition 2, the project reported installation of a temporary eel trap. For Condition 3, the project reported ongoing recreation planning activities. For Conditions 4 and 5, the project reported on the status of FERC relicensing, still in progress.  For Condition 6, the project reported on watershed activities.


Certification History

December 14, 2022: The Vernon project’s LIHI Certificate has been extended again until December 31, 2023 in order to continue to allow LIHI to address the unique situation of a recertification taking place at a time within a FERC relicensing when studies have been completed but no agency recommendations are available yet.

December 16, 2021: The Vernon project’s LIHI Certificate has been extended again until December 31, 2022 in order to allow LIHI to address the unique situation of a recertification taking place at a time within a FERC relicensing when studies have been completed but no agency recommendations are available yet.

December 17, 2020: The Vernon project’s LIHI Certificate has been extended again until December 31, 2021 in order to allow  LIHI to address the unique situation of a recertification taking place at a time within a FERC relicensing when studies have been completed but no agency recommendations are available yet.

February 26, 2020: The Vernon project’s LIHI Certificate has been extended until December 31, 2020 in order to allow LIHI to address the unique situation of a recertification taking place at a time within a FERC relicensing when studies have been completed but no agency recommendations are available yet.

July 13, 2019:  The public comment period has closed, the application remains under review pending receipt of additional information.

July 2, 2019:  The public comment period for the Vernon recertification application has been extended to 5 pm Eastern time on July 12, 2019. All comments must be received by that time to be considered.

May 7, 2019: The Low Impact Hydropower Institute has received a complete application for Low Impact Recertification of the Vernon Hydroelectric Project.  LIHI is seeking public comment on this application.  Specifically, we are interested in knowing whether you think the Project meets the LIHI Low Impact Certification Criteria, as revised in the 2nd Edition Handbook.  Please review the program and criteria in LIHI’s revised Handbook and then review the Project’s application materials below. Comments that are directly tied to specific LIHI criteria (flows, water quality, fish passage, etc.) will be most helpful, but all comments will be considered.  Comments may be submitted to the Institute by e-mail at comments@lowimpacthydro.org with “Vernon Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420.  Comments must be received on or before 5 pm Eastern time on July 6, 2019 to be considered.  All comments will be posted to the web site and the applicant will have an opportunity to respond.  Any response will also be posted.

May 15, 2016: LIHI received notice that TransCanada Hydro Northeast Inc. was converted to a limited liability company on April 7, 2017, becoming TransCanada Hydro Northeast LLC.  On April 19, 2017, the name of the company was changed from TransCanada Hydro Northeast LLC to Great River Hydro, LLC.

October 21, 2016:  On September 19, 2016, LIHI announced the Preliminary Decision that the Vernon Station Hydroelectric Project (FERC No. P-1904) satisfies the 2014 LIHI Certification Criteria.  A 30-day appeal period was open until October 20, 2016, and no requests for appeal were received. The Vernon Station Hydroelectric project is now deemed certified by LIHI. The effective date for the Vernon Station certification is December 15, 2013 for a five (5) year term, which will expire on December 15 2018. This LIHI recertification is taking place in the middle of a very complex set of FERC relicensing proceedings, the outcome of which is not at all clear at this time.  While the current LIHI certification decision is based on findings that indicate the Vernon facility satisfies the LIHI criteria defined in the applicable, April 2014 version of our Certification Handbook, the environmental conditions in the Connecticut River are dynamic and changing — the full effects of issues such as the shutdown of the Vermont Yankee Nuclear Power Plant, the changing status of Atlantic salmon, American shad, and American eel stocks, etc., will continue to evolve. LIHI’s current decision on a new certification covering the period from 2013 to 2018 should not be interpreted as an indication that the Vernon facility’s current effects on the river basin will continue to be satisfactory over the longer-term future.  The next time that Vernon comes due for recertification, LIHI’s decision will be based either on the new, 2nd Edition Certification Handbook or on subsequent revisions if they occur.  LIHI strongly encourages the Vernon owner to work with all stakeholders in the basin to reach long-term, sustainable solutions to water management that will produce positive outcomes for both clean energy and the environment.

September 19, 2016:  LIHI Executive Director Michael J. Sale announced a Preliminary Certification Decision that the Vernon Station Hydroelectric Project (FERC No. P-1904) satisfies the 2014 LIHI Certification Criteria and will be issued a new LIHI certification with an expiration date of December 15, 2018. This certification decision was made by the LIHI Governing Board’s Technical Committee after a full review of the Application Reviewer’s report, all public comments and additional materials provided by the Applicant. Once final, the effective certification date for the Vernon Station Project is December 15, 2013 for a five (5) year term, which will expire on December 15, 2018. As provided for in Section 4.2.5 of the LIHI 2nd Edition Handbook, the Preliminary Certification Decision to certify, along with the Application Reviewer’s report will be posted on the Institute’s Web page for 30 days.  The Application Reviewer Report and all the application materials are available at the bottom of the page. Individuals or organizations that commented on the initial Application Package (“Commenter”) may submit a letter to the Executive Director requesting an appeal within the 30-day period beginning on September 19, 2016, and closing on October 18, 2016. The appeal request must state specific reasons why the hydropower facility should have failed one or more criteria. If an individual or organization did not comment on the initial Application Package, they may not file an appeal.

January 27, 2014: The Low Impact Hydropower Institute has received an application from TransCanada for a second term of certification of the Vernon Station Hydroelectric Project. The 2013 application was received on December 5th, but due to administrative backlog, the certificate has been granted a three month extension beyond the date of December 15th. The application materials can be found in the “Files” section below.

June 25, 2009: The Vernon Station Hydroelectric Project has been certified as low impact for a five year term, effective December 15, 2008 and expiring December 15, 2013.


Certification Files

2018-2019 Recertification

2013-2016 Recertification

2008 Certification


Key Documents