LIHI Certificate #15 – Bowersock Mills Project, Kansas

Project Name Bowersock Mills
LIHI Certificate No. 15
LIHI Certificate Term July 9, 2019 – July 8, 2029
Owner Bowersock Mills and Power Company
State Kansas
Location Located at river mile 52.4 on the Kansas River in the city of Lawrence, Douglas County, Kansas.
Installed Capacity 7 MW total – N. Powerhouse 4.65 MW, S. Powerhouse 2.35 MW
Average Annual Generation 22,277 MWh
Facility Type Run-of-river
FERC No. P-13526 issued in 2010, expires 07/31/2060

The Bowersock Mills Project is located on the Kansas River in Lawrence, Kansas. The project is the only FERC licensed hydroelectric project in Kansas. The Bowersock Mills & Power Company (BMPC) was first established in 1874 as a milling operation on the Kansas River. At that time, Lawrence faced an energy crisis, as all the wood within a day’s wagon-haul had been harvested, driving the cost of energy significantly higher. Orlando Darling operated a grist mill on the north side of the Kansas River, and working with the City of Lawrence, agreed to build a dam across the Kansas River. Darling went broke in his efforts to make the dam hold, as did the subsequent company that tried to complete the dam. By that time, the Douglas County Flour Mills had been established on the south side of the river and was operating off the still-standing flume and southernmost masonry portion of the dam. J.D. Bowersock, the operator of the Douglas County Flour Mills, took over the project and successfully completed the dam. Bowersock continued to mill flour from that location and to provide mechanical energy for the City of Lawrence. Operations of the mill and mechanical energy generation continued until the flood of 1903 tore out the flour mill building and associated mechanical energy apparatus.

Bowersock built a new powerhouse (South Powerhouse) between 1903 and 1905. The South Powerhouse was one of the earliest projects to generate hydroelectric energy in the United States and still generates power today. The North Powerhouse was constructed in 2012.

The Bowersock dam is 655 feet long from the north side of the south powerhouse flume to the north powerhouse with an approximate height of 17.08 feet. The southern 1/3 of the dam is a masonry block dam. The body of the dam is approximately 8 feet in width, and the downstream face of the dam in the timber crib portion has a stair-step structure, which ends in vertical sheet pile wall at various distances from the dam. The impoundment or “Millpond” is maintained at a steady level through five separate headgate structures. The South Obermeyer section consists of fifteen individual 10-foot Obermeyer flashboards and is located at the southern end of the dam. The center of the dam is topped by four separate rubber bladders, all of which operate independently from one another. The fifth control structure is the North Obermeyer Gate, which is a 20-foot gate located at the northern most end of the dam. The south powerhouse houses seven turbine/generator units and the north powerhouse houses four turbine generator units with a total installed capacity of 7 MW.

The project operates in run-of-river mode and impounds a 423-acre reservoir. Automated rubber bladders atop the dam as well as the Obermeyer gates operate to keep impoundment fluctuations within 6 inches. Flows are also monitored by a Supervisory Control and Data Acquisition system which indicates if the millpond is experiencing significant increases or decreases in flow rates. The flow regime was developed in consultation with the Kansas Department of Health and Environment (KDHE), USACE, and USFWS.

Waters within the project reach are designated as impaired for high concentrations of total suspended solids, total phosphorous, and E. coli. Via consultation with KDHE, the agency concluded that due to the project’s flow-through nature and long-standing presence on the river, the project is not introducing pollutants that cause or contribute to the impairments.

The Kansas River upstream of the project is host to a diverse fish community including ancient non-teleost species (lampreys, sturgeon, paddlefish, and gar), herring, cyprinids, suckers, catfish, sunfish, walleye, and drum. American eel is the only migratory species present in the project vicinity. However, resource agencies including USFWS and Kansas Department of Wildlife, Parks, and Tourism have not prescribed passage measures as the dam acts as a barrier to the upstream spread of Asian carp, an invasive species. The downstream reaches of the river include channel catfish, freshwater drum, common carp, largemouth bass, and white crappie.

The project lands consist of 664 acres. The project has little control of the surrounding lands that are increasing becoming more developed with urban parkland, riparian lands, and cultivated fields. No lands of significant ecological value exist in the project area.

Threatened or endangered species potentially present in the project vicinity include the mead’s milkweed, western prairie fringed orchid, pallid sturgeon, sturgeon chub, shoal chub, plains minnow, flathead chub, silver chub, sicklefin chub, western silvery minnow, snowy plover, northern long-eared bat, and eastern spotted skunk. Several bird species protected under the Migratory Birds Treaty Act and the Bald and Golden Eagle Protection Act may be observed in the project area including American bittern, American golden-plover, bald eagle, black rail, black-billed cuckoo bobolink, buff-breasted sandpiper, dunlin, eastern whip-poor-will, henslow’s sparrow, hundsonian godwit, Kentucky warbler, king rail, least bittern, lesser yellowlegs, prothonotary warbler, red-headed woodpecker, rusty blackbird, semipalmated sandpiper, short-billed dowitcher, and wood thrush. Pallid sturgeon have been noted in the downstream reach of the project several decades ago, but resource agencies decided against passage prescriptions at the project due to the presence of Asian carp. USFWS further concluded that the project operations do not adversely impact sturgeon. Kansas has a single recovery plan for sicklefin chub, sturgeon chub, and western silvery minnow. These management activities primarily pertain to reducing impacts to critical habitats which the project accounts for in their run-of-river operations. The project has a 200-foot buffer around the river and powerhouse lands, which mitigates any impact to terrestrial species.

No cultural or historic resources are currently found in the project area. The Kansas Historical Society has noted that the construction and operation of the project does not impact any cultural or historic resources.

Recreational resources at the project include a footpath and canoe portage trail, fishing deck, and information kiosk. Public access is provided free of charge.


Compliance Status

There are no facility-specific conditions in the current Certificate

2023: No material changes or compliance issues were identified.  The project remains in compliance based on the annual review.

2022: No material changes were identified.  The project reported rubber dam failure in 2021 that led to a sudden impoundment drawdown.  A subsequent drawdown to make repairs resulted in a planned impoundment deviation.  These deviations were properly reported to FERC and resource agencies, appropriate actions were taken, and there were no environmental effects. Therefore, LIHI does not consider this a significant compliance issue.

2021: There were no reported changes or compliance issues. The project remains in compliance based on the annual review.

2020: Annual reporting for the current Certificate has not yet taken effect.


Certification History

January 1, 2022: The LIHI Certificate term has been extended in accordance with Revision 2.05 of the LIHI 2nd Edition Certification Handbook issued January 1, 2022. Refer to the facility table above for the new term.

August 3, 2020: The decision to recertify the Bowersock Mills Project became final after the close of the appeals period on August 1, 2020 with no appeals filed. The Certification term is from July 9, 2019 – July 8, 2024.

July 2, 2020:  The Low Impact Hydropower Institute (LIHI) has preliminarily approved the Bowersock Mills Project for a new 5-year term of Low Impact Certification. This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Bowersock Mills Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on August 1, 2020. The full application and reviewer’s report are available below. If no appeal requests are received and the decision becomes final, the Certification term for the Project will be July 9, 2019 through July 8, 2024.

April 27, 2020: The Low Impact Hydropower Institute has received a complete application for Low Impact recertification of the Bowersock Mills Hydroelectric Project.   The complete application can be found below. LIHI is seeking public comment on this application. Comments that are directly tied to specific LIHI criteria (flows, water quality, fish passage, etc.) will be most helpful, but all comments will be considered.  Comments may be submitted to the Institute by e-mail at comments@lowimpacthydro.org with “Bowersock Mills Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420.  Comments must be received on or before 5 pm Eastern time on June 26, 2020 to be considered.  All comments will be posted to the web site and the applicant will have an opportunity to respond.  Any response will also be posted.

September 25, 2015: LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board, has determined that the Bowersock Hydroelectric Project (FERC No. 13526) continues to meet the LIHI Certification Criteria. The effective certification date for the Bowersock Project is July 9, 2014 for a five (5) year term, which will expire on July 9, 2019, with the following condition:

  • Satisfied in 2020. Condition 1. The facility owner shall provide LIHI with a brief report on the status and progress on the current recreational plan for the facility.  This summary report shall be due as part of the next annual Compliance report to LIHI.  If the progress on the recreational plan is deemed satisfactory at that time, this condition will be removed.

April 20, 2015:  On April 16, 2015 LIHI received a complete application from the Bowersock Mills and Power Company (BMPC) for an additional term of certification of the Bowersock Mills Hydroelectric facilities.  The application materials were delayed because the facilities underwent material changes, and BMPC required additional time to gather documentation and supportive materials.  The 2014 application is provided below.

January 27, 2010: It has been determined by LIHI’s Governing Board that the Bowersock Project continues to meet the Certification Criteria. The project has been recertified for a five year term, effective July 9, 2009 and expiring July 9, 2014.

October, 2004: The Bowersock Mills Project has been certified as low impact for a five year term, effective July 27, 2004 and expiring July 27, 2009.


Certification Files

2020 Recertification

2015 Recertification

2009 Recertification

2004 Certification


Key Documents