Buffalo River Project, LIHI #21 – Complete Application Received
December 8, 2021Final Decision – Certification of the Upper La Chute and Lower La Chute Projects, LIHI #185, 186
December 14, 2021December 14, 2021: The Low Impact Hydropower Institute (LIHI) has preliminarily approved the Benton Falls Project located on the Sebasticook River in Maine for a 5-year term of Low Impact Certification.
This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Benton Falls Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 1167 Massachusetts Ave, Office 407, Arlington, MA 02476. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on January 13, 2022. The full application and reviewer’s report are available HERE.
If no appeal requests are received and the decision becomes final, the Certification term for the Project will be November 23, 2020 through November 22, 2025.
Preliminary Decision – Certification of the Wells Dam Project, pending LIHI #203, WA