LIHI Certificate #29 - Jordanelle Project, Utah

Project Name Jordanelle
LIHI Certificate No. 29
LIHI Certificate Term June 10, 2023 – June 9, 2033
Owner Central Utah Water Conservancy District
State Utah
Location Located at river mile 49 on the Provo River in Wasatch County, approximately four miles north of Heber City, Utah.
Installed Capacity 13 MW
Average Annual Generation 43,000 MWh
Facility Type store and release
FERC No. n/a, FERC non-jurisdictional

The Jordanelle Project is located on the Provo River in Wasatch County, north of Heber City, Utah. The Project is not licensed by the Federal Energy Regulatory Commission (FERC) but is authorized through a lease of power privilege from the Department of the Interior (DOI), Bureau of Reclamation’s (USBR) Central Utah Project (CUP).

A lease of power privilege grants a non-federal entity the right to utilize, consistent with the CUP purpose, waterpower head and storage at and/or operationally in conjunction with the CUP, for non-federal electric power generation and sale by the entity. The general authority for lease of power privilege under USBR legal statutes includes among others, the Town Sites and Power Development Act of 1906 and the Reclamation Project Act of 1939.

Jordanelle Dam was not primarily built for energy production. The dam is used for the delivery of water downstream for municipal, industrial, irrigation, and water quality purposes in Salt Lake City and the northern Utah County. Other uses include flood control, recreation, fish and wildlife enhancement, and power generation.

Jordanelle Dam is a rolled earthfill structure with a fuse plug emergency spillway and outlet works. The rolled earth embankment section has a structural height of 300 feet and a crest length of 3,820 feet. The emergency fuse plug spillway is located near the left abutment and consists of an unlined inlet channel, a concrete lined trapezoidal channel, an earthen plug section, a concrete chute, and a 9.5-foot by 10-foot concrete double box conduit. The powerhouse is a reinforced concrete structure located partially within the rock berm at the toe of the dam, west of the existing outlet works. The penstock is constructed from the 72-inch-diameter connection in the outlet conduit and then routed to the powerhouse where it bifurcates into two 66-inch-diameter pipes feeding the turbines.

The floor of the powerhouse is set at an elevation below the tailwater elevation. This elevation requires maintenance to be performed on the turbines with tail bay gates installed. Maintenance can be accomplished without the need to de-water the tailrace. The turbines, generators, and all mechanical equipment are located at this level. The turbines discharge into a tailrace channel below the turbine floor.

The major equipment located on the turbine floor includes two horizontal Francis turbine/generator units with a total installed capacity of 13 MW; turbine controllers; turbine inlet valves located on the penstock to each turbine; a hydraulic power unit for each unit and valve; and sump pumps. The powerhouse arrangement includes a control room area. A control room is required to house the control panels, switchgear, motor control center, panel boards, batteries, and battery chargers. The control room is isolated from the turbine floor and sound-proofed to provide a quiet space for the operator. It is located above the turbine floor to protect the equipment from potential flooding and is located near the plant substation to minimize conduit and cable runs.

The project operates in a store-and-release mode and is sited at a reservoir controlled by the USBR. The project itself is not responsible for reservoir management and does not have any effect on the operation of the Jordanelle Dam and reservoir.

Waters within the project reach are designated as Class 1C, 2A, 3A, and 4:

  • 1C: Protected for domestic water supply purposes with prior treatment processes as required by Utah Department of Environmental Quality.
  • 2A – Protected for primary contact recreation such as swimming.
  • 3A – Protected for cold water species of game fish and other cold-water aquatic life, including the necessary aquatic organisms in their food chain.
  • 4 – Protected for agricultural uses including stock watering and irrigation of crops.

The reservoir is a public water system for the state of Utah used for the above designations. The project reaches are designated as impaired for pH. Water is released from the dam through a selective level (SLOW) and/or low level (LLOW) inlet structure through piping and tunnels to the outlet works.  Water is mixed from different reservoir depths to control and meet water quality standards for phosphorus, temperature, and dissolved oxygen levels in water discharged.

No anadromous or catadromous fish are present in the project area. The river drains to Utah Lake which then drains to the Jordan River and ultimately to the Great Salt Lake which has no outlet to the ocean.  The project itself does not present a barrier to downstream passage of resident fish, but flows released from the dam are of too high a velocity to support passage. Resident species in the Jordanelle Reservoir include Brown Trout, Kokanee Salmon, Rainbow Trout, Smallmouth Bass, Utah Chub, Wiper, Yellow Perch, Black Crappie, Cutthroat Trout/Bonneville, Largemouth Bass, Splake, Tiger Muskie, and Utah Sucker. As acceptable mitigation, the Provo River Restoration Project mitigates past impacts of the Central Utah Project and other federal Reclamation projects by improving fish and riparian habitats in the 10-mile reach of the Provo River downstream.

The hydro project does not directly manage the shoreline or watershed areas in their operation of the hydroelectric facility.  The impoundment shoreline is controlled and maintained by Jordanelle State Park under a reservoir management plan developed by USBOR.  The shorelines of the downstream reach are controlled and maintained by Wasatch County.  The reach is bounded on the east and west by major roads with little development. The Provo River Restoration Project maintains, monitors, and improves the shorelines and habitats in this reach.

Threatened or endangered species potentially present in the project vicinity include the bald eagle, golden eagle, Canada lynx, yellow-billed cuckoo, Ute ladies’ tresses, and June sucker.  While the Canada lynx has been spotted in the project area once since 2004, no critical habitat for the species occurs in the area. The June Sucker Recovery Program that the project owner collaborates with US Fish and Wildlife Service on has seen sufficient progress in reestablishing the species.

Based on consultation with the State Historic Preservation Office and Tribal Nations, there are no cultural resources present at the project and no historic properties are affected by the project.

The project’s water supply security measures preclude access to the hydro project as it is in a protected area not open to the public. However, the reservoir is considered a world-class fishery and the area is managed by Utah State Parks. Free recreation access and facilities are provided below the project.


Compliance Status

There are no facility-specific conditions in the current Certificate.

2024: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.

2023: Annual reporting for the current certificate has not yet taken effect.


Certification History

February 2, 2024: The Low Impact Hydropower Institute has issued a final decision on the recertification of the Jordanelle Hydroelectric Project, after the close of the appeal period with no appeal requests received.  The new certification term is June 10, 2023 through June 9, 2033.

December 4, 2023: The Low Impact Hydropower Institute has preliminarily approved Low Impact recertification for the Jordanelle Dam Hydroelectric Project. The full application and reviewer’s report are available below. This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Jordanelle Dam Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 1167 Massachusetts Ave, Arlington, MA 02476. All requests will be posted to the website. The applicant will have an opportunity to respond, and any response will also be posted. Requests must be received by 5 pm Eastern time on January 3, 2024. If no appeal requests are received the certification term will be June 10, 2023 through June 9, 2033.

September 14, 2023: The Low Impact Hydropower Institute (LIHI) has received a complete recertification application from Central Utah Water Conservancy District for the Jordanelle Project. The application is found below in the Certification Files section. LIHI is seeking comment on this application. Comments that are directly tied to specific LIHI criteria (flows, water quality, fish passage, etc.) will be most helpful, but all comments will be considered. Comments may be submitted to LIHI by e-mail at comments@lowimpacthydro.org with “Jordanelle Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 1167 Massachusetts Avenue, Arlington, MA 02476. Comments must be received at the Institute on or before 5 pm Eastern time on November 13, 2023 to be considered. All comments will be posted to the web site and the applicant will have an opportunity to respond. Any response will also be posted.

June 10, 2016: LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board, has certified that the Jordanelle Hydroelectric Project satisfies the LIHI Certificate Criteria. A Preliminary Decision was announced on May 6, 2016, and a 30-day appeal period was open through June 6, 2016. No requests for appeal were received. The effective certification date for the Jordanelle Project is June 10, 2015 for an eight (8) year term, which will expire on June 10, 2023. The Certificate includes the following facility-specific condition:

  • Condition 1: The facility owner shall continue to work proactively with the USFWS on the June Sucker Recovery Program. As part of its annual compliance letter to LIHI, the owner shall provide a statement confirming that it has released the committed flows identified in its June Sucker Recovery Implementation Program (JSRIP) from the Jordanelle Project for the recovery of the June sucker during the prior year, within the limits of the owners Lease of Power Privilege agreement with the Bureau of Reclamation. Also, verification shall be provided annually that the owner has discussed and reached agreement with the USFWS pertaining to these releases as part of the JSRIP.

October 28, 2015: The Low Impact Hydropower Institute has received a complete application for a new term of Low Impact Certification for the Jordanelle Hydroelectric project.  The application materials can be found below. The public comment period for this application closed on December 28, 2015.

June 19, 2015: The Jordanelle Dam Hydroelectric project has been granted an extension of the current certificate term. The new expiration date is December 31, 2015. See 2015 Recertification Extension Letter for explanation below.

December 13, 2007: The Jordanelle Dam Hydroelectric Project has been certified as low impact for an eight year term, effective June 10, 2007 and expiring June 10, 2015.

June 10, 2007: The Central Utah Water Conservancy District (CUWCD) has submitted an application for certification of the Jordanelle Dam Hydroelectric Project. A comment period will remain open for 60 days, until August 10, 2007.


Certification Files

2023 Recertification

2015 Recertification

2007 Certification