LIHI Certificate #102 - Putts Bridge Project, Massachusetts

项目名称 | Putts Bridge |
LIHI 证书编号 | 102 |
LIHI 证书期限 |
December 20, 2023 – December 19, 2033 |
所有者 | Central Rivers Power MA, LLC,LS Power/ Patriot Hydro, LLC 的子公司 |
状态 | 马萨诸塞州 |
地点 | Located at approximate river mile 9.2 on the Chicopee River in the Towns of Wilbraham and Ludlow and City of Springfield in Hampden County, Massachusetts. |
装机容量 | 3.9 MW |
平均年发电量 | 13,713 MWh |
设施类型 | 河流径流 |
联邦能源管理委员会 不。 | P-10677 exempt 1992 |
The Putts Bridge Project is located on the Chicopee River in the Towns of Wilbraham and Ludlow, and the City of Springfield in Hampden County, Massachusetts. The Project 坝 crosses the town line between Springfield and Ludlow; the 发电站 is located in Ludlow. The impoundment extends in a northeasterly direction, bordering Springfield and Ludlow. The Project was originally constructed in 1918 by the Ludlow Manufacturing Company.
尽管奇科皮河只有 18 英里长,但其流域面积却达到 721 平方英里,是马萨诸塞州最大的流域,也是康涅狄格河最大的支流。在工业革命期间,奇科皮河成为水力发电的热门目的地,主要是因为其流域落差达 260 英尺。
The Putts Bridge project is situated upstream of three other hydroelectric facilities located on the Chicopee River and downstream of two other dams on the Chicopee River as well as other dams on the Ware, Swift and Quaboag Rivers. The two upstream projects are 柯林斯 (LIHI #88), 和 红桥 (LIHI #96). Downstream are Indian Orchard (LIHI #112), Chicopee Falls (FERC No. 6522), and 德怀特 (LIHI #170).
The project includes a dam, concrete headgate structure, two conduits, forebay, trashrack, intake structure, a powerhouse with two generating units, a tailrace channel, appurtenant facilities.
The dam crosses the Chicopee River in a roughly north-to-south direction, and is a concrete gravity structure approximately 223 feet long by 22 feet high. The northern 邻接 of the dam is contiguous with the abutment for the Ludlow Avenue Bridge. Adjacent to this abutment are a skimming gate and a deep sluice gate. A 23-foot-long non-overflow section extends from the gate area to the 200-foot-long 弧形 泄洪道 which extends across the river to the south abutment. A concrete retaining wall extends from the south abutment for approximately 133 feet. The dam creates a 1,700-foot-long bypassed reach.
The concrete headgate structure is adjacent to the northeast abutment of the dam. Six motorized 主门, each approximately 12 feet wide by 13.3 feet high direct flow to a double-barreled, underground concrete conduit that extends 647 feet from the impoundment to the forebay. Each barrel of the conduit is 16.5 feet high by 12.5 feet wide.
The forebay is a reinforced concrete structure measuring 40 feet wide by 104 feet long. The forebay is 41.5 feet high, with a 2.5-foot diameter spigot type drain gate at the base, and an 18-foot-wide skimming gate on the north forebay. The trashrack is situated along the western forebay wall, extending from the floor of the forebay. There is a mechanical trash rake mounted on rails along the entire width of the trashrack. Wooden headgates, measuring 14.3 feet square, isolate the forebay from the generating units.
The powerhouse has a concrete substructure with a brick superstructure. It houses two operating units, No.2 and No.3, and one retired unit, No. 4. Unit No.1 was never installed although the turbine pit is there. Unit No.5 is a retired waterwheel exciter. The project has a combined capacity of 3.9 MW. The tailrace 运河 runs 355 feet from the powerhouse in a westerly direction to where the flow re-enters the Chicopee River.
该项目采用 径流 mode and impounds a 65-acre reservoir. The project provides a 25 cfs minimum flow to the bypass reach and limits impoundment fluctuations to +/- 0.25 foot. This flow regime was developed in consultation with US Fish and Wildlife Service (USFWS) and Massachusetts Division of Fish and Wildlife (MDFW).
Waters within the project reach are designated as Class B and impaired for the presence of invasive water chestnut, E coli and fecal coliform. Massachusetts Department of Environmental Protection confirmed that the project does not cause or contribute to any adverse water quality conditions.
The Chicopee River watershed is not currently the subject of migratory fish management efforts and downstream dams block access; however, American eel is found throughout the Chicopee River system. Resident fish species include bluegill, pickerel, bass, sunfish, sucker, and many more. Though not designed for 鱼道, the minimum flow gate can pass riverine fish downstream over the dam.
The project lands consist of roughly 4 acres. The shoreline consists primarily of shrub and forested 湿地 but lie outside the project boundary. No lands of significant ecological value are found within the project area.
No threatened or endangered species are potentially present in the project vicinity. Though the Northern long-eared bat has the potential to exist statewide, the project does not contain any critical habitat for the species and the urban environment is unlikely to support roosting trees.
The project itself is eligible for listing on the 国家历史遗迹名录. Consultation with the State Historic Preservation Office is required before conducting any construction activity with potential to modify existing historic facilities.
Recreational resources at the project include an informal boat ramp and fishing access on the east side of the impoundment. Public access is provided free of charge.
合规状态
该证书包括以下针对设施的特定条件:
条件 1: Should the Facility Owner receive notification during the term of this LIHI Certification from either the USFWS or MDFW that upstream and/or downstream passage for anadromous or 洄游性 fish is required, based on sound science / technical data that has shown that such passage is required at the Putts Bridge Project, the Facility Owner shall forward a copy of that notification and its response to LIHI within 45 days of receipt of the notification.
条件2: Should the Facility Owner determine that ground disturbance or significant changes in project operations are desired during the term of this LIHI Certification that could affect habitat for the swamp dock, the Facility Owner shall conduct studies and filings deemed necessary by the state to determine impacts to swamp dock that may occur in the Project area. LIHI shall be provided copies of agency communications (e.g., approvals, denials, mitigation measures, etc.) associated with such desired Project changes. This information should be submitted as part of the LIHI annual compliance statements.
2024: No material changes or compliance issues were identified. The project remains in compliance based on the annual review. For Conditions 1 and 2, the project reported no activity.
2023: Annual reporting for the current Certificate has not yet taken effect.a
认证历史
2024 年 1 月 3 日: 低影响水电研究所已就红桥、普茨桥、印第安果园和德怀特水电项目的中期重新认证作出了最终决定。这些项目位于马萨诸塞州的奇科皮河上。初步决定于 2023 年 11 月 28 日宣布,开启了为期 30 天的上诉期。该窗口于 2023 年 12 月 28 日关闭,没有提出上诉。因此,重新认证项目的决定现已最终确定。新项目期限如上表所示,完整的中期审查申请和审查报告可在下方找到。
2023 年 11 月 28 日: 低影响水电研究所已初步批准对位于马萨诸塞州奇科皮河上的红桥、普茨桥、印第安果园和德怀特项目水电项目进行低影响重新认证。该决定是初步决定,有待 30 天的上诉期结束。只有在 60 天的评论期内对初始申请发表评论的人才有资格提出上诉。此类上诉需要包括对项目不符合 LIHI 标准的解释。上诉请求可以通过电子邮件提交至 comments@lowimpacthydro.org 主题行中请注明“Chicopee River Projects”,或邮寄至 Low Impact Hydropower Institute,地址为 1167 Massachusetts Ave, Arlington, MA 02476。所有申请都将发布在网站上。申请人将有机会作出回应,任何回应也将发布。 请求必须在 2023 年 12 月 28 日东部时间下午 5 点之前收到。 The consolidated review report can be found below. If no appeal requests are filed, the new certification term will be December 20, 2023 – December 19, 2033.
2023 年 8 月 17 日: 位于马萨诸塞州奇科皮河上的四个 LIHI 认证项目于 2023 年 3 月 13 日收到了对其 FERC 豁免的综合修订。这些项目是 Red Bridge (LIHI #96)、Putts Bridge (LIHI #102)、Indian Orchard (LIHI #112) 和 Dwight (LIHI #170)。该修订授权对每个项目的运营进行更改 达到顶峰 to run-of-river along with changes in bypass reach minimum flows at some projects. In accordance with Section 5.3.4 of the 2nd Edition LIHI Handbook, Revision 2.05, issuance of a FERC 豁免 amendment that affects the LIHI criteria constitutes a “material change” and triggers a mid-term LIHI Certification review. New Certificate terms can be granted if the projects continue to satisfy the LIHI criterion, even if the current certification terms have not yet expired. The applicant, Central Rivers Power, MA, LLC (a subsidiary of LS Power/ Patriot Hydro, LLC), has submitted a summary of the operational changes related to the FERC exemption amendment. Documents are available in the Certification Files Section of each project webpage:
- 红桥 – LIHI #96
- Putts Bridge – LIHI #102 – see files below.
- 印度果园 – LIHI #112
- 德怀特 – LIHI #170
正在开放为期 60 天的公众评论期,让利益相关者对提交的内容发表评论。收到的所有评论都将纳入中期审查报告,发布在 LIHI 网站上,并纳入重新认证项目的初步决定中。 评论可发送至 mailto:comments@lowimpacthydro.org 主题行中写着“奇科皮河项目”。 评论必须在 2023 年 10 月 16 日东部时间下午 5 点之前收到。
2022 年 1 月 1 日: LIHI 证书期限已根据 2022 年 1 月 1 日发布的 LIHI 第 2 版认证手册 2.05 版延长。有关新期限,请参阅上面的设施表。
2019年8月8日: The decision to recertify the Putts Bridge Hydroelectric Project is final. No appeals were received during the appeal period which closed on July 19, 2019. The new certification term for the Project is from December 20, 2017 through December 19, 2022.
June 19, 2019: The Low Impact Hydropower Institute has preliminarily approved Low Impact Certification for the Putts Bridge Hydroelectric Project. This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Putts Bridge Hydroelectric Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on July 19, 2019. The full application and reviewers report are available below. If no appeal requests are received and the decision becomes final, the Certification term for the Project will be December 20, 2017 for a five (5) year term which will expire on December 19, 2022.
April 8, 2019: The Low Impact Hydropower Institute has received a complete application for Low Impact Recertification of the Putts Bridge Hydroelectric Project. LIHI is seeking public comment on this application. Specifically, we are interested in knowing whether you think the Project meets the LIHI Low Impact Certification Criteria, as revised in the 2nd Edition Handbook. Please review the program and criteria in LIHI’s revised 手册 然后查看以下项目的申请材料。与特定 LIHI 标准(流量、水质、鱼类通道等)直接相关的评论将最有帮助,但所有评论都会被考虑。评论可以通过电子邮件提交给研究所 comments@lowimpacthydro.org with “Putts Bridge Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420. Comments must be received on or before 5 pm Eastern time on June 7, 2019 予以考虑。所有评论都将发布到网站上,申请人将有机会作出回应。任何回应也将发布。
2013年3月12日: The Putts Bridge Hydroelectric Project has been certified as low impact for a five year term, effective December 20, 2012 and expiring December 20, 2017.
February 18, 2013: The public comment period on application has closed.
December 20, 2012: Essential Power LLC has submitted an application for the certification of the Putts Bridge project. Application has been posted and the public comment period has opened.
认证文件
2023年中期审查
2019 年重新认证
- Putts Bridge Recertification Review Report 2019
- Putts Bridge Recertification Application
- Aerial Photograph of Putts Bridge
- Aerial Photograph of Putts Bridge 扣押
- Aerial Photograph of Putts Bridge 绕过范围
- Aerial Photograph of Putts Bridge 尾水
- Demonstration of 最小流量 2012
- 2013 年最小流量演示
- 2014 年最小流量演示
- 2015 年最小流量演示
- 2016 年最小流量演示
- 2018 年最小流量演示
- 评分者电子邮件 2018
- 斯莱特信函 2018
- 库比特信函 2018
- Massachusetts Division of Fisheries and Wildlife Letter 2000
- Massachusetts Year 2016 Integrated List of Waters 2017
- Chicopee River Watershed Assessment 2003
- Chicopee River Watershed Action Plan 2005-2010
- US Fish and Wildlife Service – List Of Massachusetts Threatened & Endangered Species
- Putts Bridge Project – Mesa Information Request
- Putts Bridge MESA Response
2012 年认证
- Putts Bridge Report
- Putts Bridge Questionnaire
- Application Appendix – Demonstration of Minimum Flow 2012
- Application Appendix – ConEdison Development Letter 2012
- 应用程序附录 – 旁路 Study Plan 2012
- Application Appendix – Bypass Study Report 2012
- Application Appendix – Minimum Flow Monitoring Plan 2012