Certificado LIHI #140 – Proyecto Little Falls, Maine



Nombre del proyecto | Pequeñas cataratas |
Certificado LIHI No. | 140 |
Plazo del certificado LIHI | 5 de septiembre de 2017 – 4 de septiembre de 2027 |
Dueño | Presumpscot Hydro LLC, una subsidiaria de Relevate Power LLC |
Estado | Maine |
Ubicación | Windham y Gorham, condados de Cumberland Milla del río 16,9 Río Presumpscot |
Capacidad instalada | 1,0 MW |
Generación media anual | 4.200 MWh |
Tipo de instalación | de pasada |
Comisión Federal de Comercio No. | P-2941 expedido en 2003, vence el 30/09/2053 |
The Little Falls Project is located on the Presumpscot River in Cumberland County, Maine. Several mills have existed at the Little Falls site since the early 19th century. C.A. Brown and Company purchased the site in 1875 and constructed a wood board mill. Later, in the early 1900s, the Androscoggin Pulp and Paper mill purchased the property. Although Central Maine Power Company owned the power rights in the 1950s, they did not operate it. Mr. Lawrence Keddy purchased the site in the 1960s and used the power in his nearby steel mill. S.D. Warren purchased the site in 1974 (later renamed Sappi North America, Inc.). There are six hydroelectric facilities on the Presumpscot River between Sebago Lake and the Atlantic Ocean in Portland, Maine. The Little Falls project is the fifth hydro project downstream of the Sebago Lake outlet. Upstream of the project, from upstream to downstream, are the Eel Weir, Gorham del Norte (LIHI #129), Dundee, and Gambo (LIHI #139) Proyectos. El proyecto aguas abajo es Cataratas Mallison (#141).
El proyecto incluye la presa, estructura de admisión, central eléctrica, cuatro turbinas, tramo de derivación y paso de anguilas aguas arriba. La presa es una estructura de hormigón armado y mampostería de 331 pies de largo y 14 pies de alto que incorpora un puente de 160 pies de largo. aliviadero sección, un aliviadero de 101,5 pies de largo y una sección de compuerta, y una estructura de entrada de 70,5 pies de largo. Una central eléctrica de mampostería también es parte integral de la presa. Contiene cuatro Turbinas Francis Conectado directamente a generadores con una capacidad instalada total de 1 MW. El tramo de derivación tiene 300 pies de largo y se extiende entre la presa y los desagües de la central eléctrica.
El proyecto opera en régimen de pasada y confina un embalse de 29 acres. El proyecto proporciona un caudal mínimo de 26 pies cúbicos por segundo (cfs) en el tramo de derivación. El régimen de caudal se desarrolló con base en estudios realizados por el Departamento de Protección Ambiental de Maine (MEDEP) para garantizar el mantenimiento de un hábitat ribereño adecuado para los recursos pesqueros y de vida silvestre.
Las aguas dentro del alcance del proyecto se clasifican como de Clase B. Esta zona del río Presumpscot se ha visto históricamente afectada por bajos niveles de oxígeno disuelto. El monitoreo realizado por MEDEP confirma que el aumento de los caudales mínimos en el proyecto ha permitido alcanzar plenamente los estándares de oxígeno disuelto en la sección aguas abajo del río.
Las represas aguas abajo evitan pez anádromo Paso en el proyecto. Las agencias se reservan el derecho de prescribir instalaciones de paso en caso de que se cumplan los factores biológicos desencadenantes que requerirían la construcción de un paso. Las instalaciones de paso para la anguila americana se instalaron en 2007 y se han actualizado para proporcionar un acceso más eficaz para el paso de la anguila. Desde el 1 de septiembre hasta el 31 de octubre, el proyecto cierra las operaciones durante 8 horas a partir del atardecer. Esto facilita la migración río abajo de la anguila americana. Los cierres se coordinan con el Departamento de Recursos Marinos de Maine y el USFWS para determinar el momento más eficaz. Los flujos pasan por el aliviadero y garantizan una migración segura hacia el tramo de derivación.
La propiedad del proyecto consta de 2 acres sin incluir el embalse. El plan de operación y monitoreo de caudal del proyecto incluye disposiciones para mitigar la erosión mediante procedimientos de vaciado y rellenado del embalse.
Las especies amenazadas y en peligro de extinción que podrían estar en las inmediaciones del proyecto incluyen: murciélago orejudo del norte, murciélago de patas pequeñas del este, murciélago café pequeño, tortuga de arroyo, avetoro común, zarapito real, tortuga de caja del este y tortuga moteada. Las actividades que podrían afectar a las especies incluidas en la lista incluyen: eliminación de árboles grandes que puedan proporcionar hábitat de descanso para los murciélagos; exposición/deshidratación del mejillón de arroyo durante vaciados significativos y prolongados del embalse, pérdida o fragmentación del hábitat debido al desarrollo del avetoro común, el zarapito real y la tortuga moteada, captura directa de tortugas de caja para mascotas. El propietario del proyecto expresó que ninguna de estas actividades está prevista en el proyecto.
Los recursos culturales en las inmediaciones del proyecto incluyen Cumberland y Oxford Canal, el complejo Oriental Powder Mill y un sitio arqueológico. El propietario del proyecto presenta informes anuales a la Oficina de Preservación Histórica del Estado y a la Nación Indígena Penobscot en los que se detallan las actividades realizadas en el marco del plan de gestión de propiedades históricas del proyecto.
Los recursos recreativos del proyecto incluyen un sendero para transportar canoas y una rampa para botes.
Estado de cumplimiento
El Certificado incluye las siguientes condiciones específicas de la instalación:
Condición 1. El Propietario deberá actualizar a LIHI sobre las siguientes actividades en la declaración anual de cumplimiento de LIHI:
a) Estado de las pruebas de eficacia del paso de anguilas río abajo.
b) El estado de los organismos anádromos aguas arriba y aguas abajo paso de peces actividades en el Proyecto y en el Proyecto Saccarappa. Las actualizaciones deben incluir resúmenes de las consultas y recomendaciones realizadas a las agencias y las partes interesadas, cualquier cambio en los planes de paso de peces con respecto a los descritos en la solicitud de LIHI y cualquier cambio en los requisitos de paso o el cronograma de implementación en ambos Proyectos. LIHI se reserva el derecho de suspender su certificación si las agencias no determinan que se está proporcionando un paso seguro en el Proyecto y que no se han dispensado dichas necesidades de paso.
do) Un resumen de cualquier consulta con MIF&W y/o USFWS relacionada con especies incluidas en la lista estatal o federal identificadas como posiblemente presentes en el sitio y que podrían verse afectadas por actividades de construcción u operaciones no rutinarias o actividades de mantenimiento. Esto también incluiría las reducciones de los niveles de los embalses que expondrían una parte importante del fondo del río, entre otras actividades no rutinarias. También se proporcionará un resumen de las actividades desencadenantes relevantes y las medidas implementadas durante el año para proteger dichas especies.
d) El estado de finalización de la salida/entrada del portage pendiente o una alternativa viable. También se proporcionará una copia de la aceptación de la FERC de la solicitud de prórroga de diciembre de 2017 y la aceptación posterior de la FERC de la instalación completada cuando esté disponible.
2025: No material changes or compliance issues were identified. The project remains in compliance based on the annual review. For Condition 1a the project reported conducting up/downstream eel effectiveness testing in 2024 and doing so in 2025. For Condition 1b, the project filed annual reports with FERC and noted that MDMR efiled the 2024 Saccarappa Falls Paso de peces Passage Effectiveness Year 2 study report on April 3, 2025. For Condition 1c the project began work on rerouting the transmission lines, as approved in the July 28, 2025 FERC Order. Surveys were completed to ensure that no northern long-eared bats or whorled pogonia were present prior to work beginning. For Condition 1d, the project reported no change in status.
2024: No se identificaron cambios materiales ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. El proyecto presentó su informe de efectividad del paso de anguilas río arriba. En cuanto a la condición 1, el proyecto no informó cambios en su estado.
2023: No se identificaron cambios materiales ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. El proyecto informó que los estudios de efectividad del paso de anguilas río arriba se completaron en 2023. En cuanto a la condición 1, el proyecto no informó cambios en el estado.
2022: No se identificaron cambios materiales ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos de la revisión anual. El proyecto informó que presentó un plan de estudio de efectividad del paso de anguilas río arriba ante el MDMR y está esperando comentarios. Para la Condición 1b, el proyecto informó que el MDMR realizó pruebas de trampas y etiquetas en 2022 en Saccarappa escala de peces con otro año de pruebas planeado para 2023. Para las Condiciones 1a, 1c y 1d, el proyecto no informó cambios en su estado.
2021: No se informaron cambios ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. En el caso de la condición 1a, el proyecto informó que está esperando los comentarios de la agencia sobre las necesidades de pruebas de eficacia, con demoras debido a la COVID. En el caso de la condición 1b, el proyecto informó que se completó la eliminación de la presa de Saccarappa y el paso de peces. En el caso de la condición 1c, el proyecto no informó ninguna actividad. En el caso de la condición 1d, el proyecto informó que recibió otra extensión de la FERC debido a problemas en curso en el sitio de desechos peligrosos.
2020: No se informaron cambios ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. En el caso de la condición 1a, el proyecto informó que la interacción con la agencia sigue en curso debido a las demoras debido a la COVID. En el caso de la condición 1b, el proyecto informó que la remoción de la presa de Saccarappa y la instalación de la escalera para peces estaban en curso. En el caso de las condiciones 1c y 1d, el proyecto no informó cambios en el estado.
2019: No se informaron cambios ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. En el caso de la condición 1a, el proyecto informó que se había planificado una reunión de la agencia para el estudio. En el caso de la condición 1b, el proyecto informó que se había iniciado la remoción de la presa Saccarappa. En el caso de las condiciones 1c y 1d, el proyecto no informó cambios en el estado.
2018: No se informaron cambios ni problemas de cumplimiento. El proyecto sigue cumpliendo con los requisitos según la revisión anual. Para la condición 1a, el proyecto no informó cambios en su estado. Para la condición 1b, el proyecto informó la presentación ante la FERC de la solicitud de renuncia a la licencia del proyecto Saccarapa. Para la condición 1c, el proyecto no informó cambios en su estado. Para la condición 1d, el proyecto informó que solicitó una extensión para completar el transporte debido a la proximidad de un sitio de desechos peligrosos.
Historial de certificaciones
1 de enero de 2022: El plazo del Certificado LIHI se ha extendido de acuerdo con la Revisión 2.05 del Manual de Certificación LIHI 2.ª Edición emitido el 1 de enero de 2022. Consulte la tabla de instalaciones anterior para conocer el nuevo plazo.
5 de marzo de 2018 – El plazo de apelación de 30 días para la decisión preliminar de certificación del Proyecto Hidroeléctrico Little Falls finalizó el 1 de marzo de 2018 sin que se recibieran apelaciones a la decisión. Por lo tanto, la decisión es definitiva y Little Falls cuenta con el Certificado LIHI #140. El plazo de certificación será del 5 de septiembre de 2017 al 4 de septiembre de 2022.
30 de enero de 2018 – El 24 de enero de 2018, el Instituto de Energía Hidroeléctrica de Bajo Impacto (LIHI, por sus siglas en inglés) aprobó preliminarmente la Certificación de Bajo Impacto para el proyecto Little Falls. Esta decisión es preliminar a la espera del período de apelación de 30 días. Solo aquellos que comentaron en el período de comentarios de 60 días de la solicitud inicial son elegibles para presentar una apelación. Dicha apelación debe incluir una explicación de por qué el proyecto no cumple con los criterios del LIHI. Las solicitudes de apelación se pueden enviar a comentarios@lowimpacthydro.org. Las solicitudes deben recibirse antes de las 5:00 p. m., hora del Este, el 1 de marzo de 2018.
7 de septiembre de 2017 – El 7 de septiembre de 2017, el Low Impact Hydropower Institute (LIHI) recibió una solicitud completa de SD Warren Company d/b/a Sappi North America para la Certificación de Bajo Impacto del Proyecto Little Falls, FERC No. P-2941.
LIHI está buscando comentarios sobre la solicitud de certificación de Little Falls. Los comentarios que estén directamente relacionados con criterios específicos de LIHI (caudales, calidad del agua, paso de peces, etc.) serán de gran ayuda, pero se tendrán en cuenta todos los comentarios. Los comentarios pueden enviarse al Instituto por correo electrónico a comentarios@lowimpacthydro.org con “Comentarios del Proyecto Little Falls” en la línea de asunto, o por correo dirigido al Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 2, Lexington, MA 02420. Los comentarios deben recibirse en el Instituto antes de las 5:00 p. m., hora del Este, el 7 de noviembre de 2017. Se considerarán todos los comentarios. Se publicarán en el sitio web y el solicitante tendrá la oportunidad de responder. También se publicarán todas las respuestas.
Archivos de certificación
Certificación 2017
- Informe de revisión de la certificación de Little Falls 2017
- Solicitud de certificación de Little Falls 2017
- Carta de comentarios de la Fundación para el Derecho de la Conservación y los Amigos del río Presumpscot: Proyectos Sappi Maine 2017
- Respuesta de Sappi a la carta de comentarios de la Fundación para el Derecho de la Conservación y los Amigos del río Presumpscot
Documentos clave
- Enmienda de la licencia FERC de 2019 para proyectos Presumpscot
- Enmienda de la licencia FERC y certificado de calidad del agua enmendado de 2017 para proyectos Presumpscot
- Enmienda de la licencia FERC y certificado de calidad del agua enmendado de 2016 para proyectos Presumpscot
- Acuerdo de conciliación de los proyectos Presumpscot de 2016
- Licencia FERC y certificado de calidad del agua de Little Falls 2003
- Proyectos Presumpscot Declaración de impacto ambiental de la FERC 2002 Parte 1
- Proyectos Presumpscot Declaración de impacto ambiental de la FERC 2002 Parte 2