LIHI Certificate #179 – White River Lock and Dam No. 1 Project, Arkansas

Nom du projet Écluse de White River et Barrage No. 1
Numéro de certificat LIHI 179
Durée du certificat LIHI 9 juin 2021 – 8 juin 2031 (option de prolongation jusqu'au 8 juin 2034)
Propriétaire City of Batesville, AR
État Arkansas
Emplacement River mile 299.2 on the White River
Capacité installée 4,3 MW
Génération annuelle moyenne 17,222 MWh
Type d'établissement Au fil de l'eau
Fédération internationale de radio-télévision (FERC) Non. P-4204, issued in 1986 expires 01/31/2036.

White River Lock and Dam No. 1, Lock and Dam No. 2 (LIHI #180), and the Écluse et barrage n° 3 « Shelby M. Knight » (LIHI #181) Hydroelectric Projects (e.g., LD1, LD2, LD3) are collectively known as the “White River Hydroelectric Project” and are located on the White River in north central Arkansas. The Projects are located at existing and no longer used US Army Corps of Engineers (USACE) locks and dams on the 722-mile-long White River. The river begins in northwestern Arkansas in the Boston Mountains and flows east toward Fayetteville where it then turns north. The river enters Missouri near Eureka Springs. It then flows southeast back into Arkansas past Bull Shoals, Mountain Home, and Calico Rock. At Batesville, the second section of the river, known as the Lower White, begins. From Batesville, the river flows south for 295 miles through Arkansas’s Delta region before emptying into the Mississippi River. The river passes multiple lakes created by eight USACE dams. Six lakes are operated together as a system to reduce the frequency and severity of floods.

Between 1900 and 1908, USACE built the three timber-crib and concrete dams and locks associated with the projects. The locks were used for navigation, moving boats containing shipments of timber, cotton, and mining products such as limestone and silica. By the mid-1950s, trains had replaced boats as the primary method for transporting these products. USACE decommissioned the locks and sold the properties. Development of the new hydropower capacity involved a utility, a college, a city, a county, the U.S. Congress, 27 years, a myriad of engineers and lawyers, and lots of tenacity and perseverance by a dedicated group of individuals. Project construction began in 2003 and the projects came online in 2006-2007. LD1 is the most downstream of the three projects, located in Batesville, AR in Independence County at river mile 299.2.

LD1 consists of a 660-foot-long, 27.6-foot-high barrage that creates an impoundment with a surface area of 773 acres. The centrale contains a single vertical Kaplan turbine and generating unit with a capacity of 4.3 MW and a design flow of 3,180 cubic feet per second (cfs) and estimated annual generation of 17,200 MWh.

An open-buse tailrace conveys water back to the river about 280 feet downstream of the dam. The Project boundary encompasses the high-water mark and about 25 acres of land around Project structures.

The project is operated in an instantaneous au fil de l'eau mode. Les débits entrants pour LD1, LD2 et LD3 dépendent du débit sortant des barrages USACE en amont de Bull Shoals sur la rivière White et du lac Norfolk sur la rivière North Fork, ainsi que d'autres affluents. Il n'y a pas déversoir portes à aucun des barrages. Les capacités de débit des usines sont faibles par rapport au débit du fleuve et les niveaux de retenue descendent rarement au-dessus ou en dessous du niveau maximal. déversoirs. Au fil de l'eau le fonctionnement et les débits sont surveillés sur la base de la jauge USGS le long de la rivière White à Batesville, AR.

Les eaux à portée des trois installations sont répertoriées comme favorisant la propagation des poissons et de la faune, les ressources primaires et loisirs de contact secondaire, ainsi que pour l'approvisionnement en eau domestique, agricole et industrielle. Une surveillance de la qualité de l'eau a été menée de 2014 à 2019 afin de garantir que les installations n'avaient pas d'impact négatif sur l'oxygène dissous et la température de l'eau dans le secteur du projet.

La construction originale des installations d'écluse et de barrage comprenait passage des poissons échelles ou passes à poissons. However, only remnants of these facilities currently remain. High flows and flooding in the project area would certainly destroy any attempt to provide permanent fish passage at the projects. Arkansas Game and Fish Commission (AGFC) and the project owner have been in contact to discuss the potential for seasonal fish passage structures though no formal recommendations or prescriptions have been provided. Resident fish species include rainbow and cutthroat trout, (stocked annually in the Bull Shoals Lake) crappie, black bass, white bass, catfish, brook trout, shad, and walleye. Trout are not native to Arkansas, but the fisheries have been noted to be a result of the cold water discharge from the USACE dams along the White River.

The project lands consist of roughly 25 acres. The property surrounding LD1 is mostly urbanized and industrial. An Erosion and Sedimentation Control Plan, Wildlife/Vegetation Management Plan and Zone humide/Plaine inondable Le plan de gestion et le plan de protection des rapaces ont été mis en œuvre dans le cadre des projets. Ces plans ont été examinés par l'US Fish and Wildlife Service (USFWS) et l'AGFC, sans aucun commentaire.

Threatened and endangered species potentially present in the project area include Northern long-eared bat, Indiana bat, gray bat, Eastern black rail, piping plover, red knot, Ozark hellbender, Missouri bladderpod, and running buffalo clover. No critical habitats for these species are present in the project area. Several mussel and clam species have been historically noted in the area of LD1. Surveys for the species were conducted but none were noted. USFWS reviewed the findings and noted that no impact would be had on the species.

Les écluses et les barrages ont été jugés éligibles à l'inscription sur la liste Registre national des lieux historiques and construction of the hydroelectric stations required removal of portions of the existing lock and dam structures. At that time, the Arkansas State Historic Preservation Officer (SHPO) noted this would constitute an adverse impact on the eligible properties and recommended documentation of the projects prior to demolition. LD1 required coordination with the Arkansas SHPO to record all or part of the Lock and Dam No. 1, construct a scale model as it was originally constructed and produce a film on display for visual interpretation of the historical operation. The project owner complied and produced such materials for the historical record.

Recreational resources at the project include public boat ramps upstream and downstream of the dam (developed and maintained by AGFC) with available parking and access to fishing. Small City parks are located on both banks adjacent to the dam with playgrounds, picnic areas, and fishing. Public fishing access is available at the lock wall. Public access is provided free of charge.


État de conformité

Le certificat comprend les conditions spécifiques à l'établissement suivantes :

Condition 1 : Si le propriétaire de l'installation reçoit une notification pendant la durée de cette certification LIHI de l'USFWS ou de l'AGFC indiquant que le passage en amont et/ou en aval pour les poissons anadromes ou catadrome Si du poisson est requis dans l'une des installations, le propriétaire doit transmettre à LIHI une copie de cette notification ainsi qu'un résumé des plans et un calendrier pour lancer la consultation et mettre en œuvre le passage ; et doit fournir une mise à jour de l'état d'avancement de la mise en œuvre dans les déclarations de conformité annuelles.

Condition 2 (facultatif) : si, à tout moment avant six mois avant l'expiration des conditions de certification pour chaque projet, le propriétaire met volontairement en œuvre un passage saisonnier des anguilles en amont dans un ou plusieurs des projets en l'absence d'une recommandation de l'agence dans la condition 1, LIHI examinera ces informations et déterminera s'il convient ou non d'attribuer une norme PLUS et de prolonger la durée du certificat de trois années supplémentaires.

2025: Aucun changement important ni problème de conformité n'a été identifié. Le projet demeure conforme suite à l'examen annuel. Aucun changement d'état n'a été signalé.

2024: Aucun changement important ni problème de conformité n'a été identifié. Le projet demeure conforme suite à l'examen annuel. Aucun changement d'état n'a été signalé.

2023: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.The project reported no change in condition status.

2022: Aucun changement important ni problème de conformité n'a été identifié. Le projet demeure conforme suite à l'examen annuel. Aucun changement d'état n'a été signalé.

2021:  Le rapport annuel pour le certificat actuel n’est pas encore entré en vigueur.


Historique des certifications

1er janvier 2022 : La durée du certificat LIHI a été prolongée conformément à la révision 2.05 du manuel de certification LIHI 2e édition publié le 1er janvier 2022. Reportez-vous au tableau des établissements ci-dessus pour connaître la nouvelle durée.

3 août 2021 : The Low Impact Hydropower Institute has issued a final decision on the certification of the White River Lock and Dam No. 1 Project located on the White River in Arkansas. The 30-day appeal window closed on July 31, 2021 and no appeals were filed. Therefore, the decision to certify the project is now final. The new term is June 9, 2021 through June 8, 2026.

1er juillet 2021 : Le Low Impact Hydropower Institute (LIHI) a approuvé la certification à faible impact (LIHI #179, #180, #181) pour les projets hydroélectriques n° 1, n° 2 et n° 3 de l'écluse et du barrage de White River, situés sur la rivière White, en Arkansas. Cette décision est provisoire, dans l'attente d'un délai d'appel de 30 jours. Seuls les participants ayant commenté la demande initiale pendant ce délai de 60 jours sont autorisés à déposer un recours. Ce recours doit inclure une explication expliquant en quoi le projet ne répond pas aux critères du LIHI. Les demandes de recours peuvent être soumises par courriel à l'adresse suivante : commentaires@lowimpacthydro.org avec « White River Project » en objet, ou par courrier adressé au Low Impact Hydropower Institute, 1167 Massachusetts Ave, Arlington, MA 02476. Toutes les demandes seront publiées sur le site web. Le demandeur aura la possibilité de répondre, et toute réponse sera également publiée. Les demandes doivent être reçues avant 17 h, heure de l’Est, le 31 juillet 2021. Le dossier complet et le rapport d'évaluation sont disponibles ci-dessous. En l'absence de recours, la période de certification pour chaque projet sera du 9 juin 2021 au 8 juin 2026, sauf prolongation conformément à la condition 2.

27 avril 2021 : Le Low Impact Hydropower Institute a reçu une demande complète de certification à faible impact pour le projet hydroélectrique de White River. Le LIHI sollicite les commentaires du public sur cette demande. Plus précisément, nous souhaitons savoir si, selon vous, le projet répond aux critères de certification à faible impact du LIHI, tels que révisés dans la 2e édition du manuel. Veuillez consulter le programme et les critères dans la version révisée du LIHI. Manuel et consultez ensuite les documents de candidature du projet ci-dessous. Les commentaires directement liés à des critères spécifiques du LIHI (débits, qualité de l'eau, passage des poissons, etc.) seront les plus utiles, mais tous les commentaires seront pris en compte. Les commentaires peuvent être soumis à l'Institut par courrier électronique à l'adresse commentaires@lowimpacthydro.org avec « Commentaires sur le projet White River » dans la ligne d'objet, ou par courrier adressé au Low Impact Hydropower Institute, 1167 Massachusetts Avenue, Arlington, MA 02476. Les commentaires doivent être reçus au plus tard à 17 h, heure de l'Est, le 26 juin 2021. à prendre en considération. Tous les commentaires seront publiés sur le site Web et le candidat aura la possibilité d'y répondre. Toute réponse sera également publiée.