Pending Application - Newbury Project, Vermont

Nombre del proyecto Newbury
Certificado LIHI No.
N / A
Plazo del certificado LIHI
N / A
Dueño Corporación de energía Green Mountain
Estado Vermont
Ubicación 0.9 River Miles from the Wells River’s confluence with the Connecticut River near the Town of Newbury, VT
Capacidad instalada 0.365 MW
Generación media anual 882 MWh
Tipo de instalación De pasada
Comisión Federal de Comercio No. P-5261 issued March 28, 2024; expires 02/29/ 2064

The Newbury Hydroelectric Project is located on the Wells River, in the Village of Wells River, Town of Newbury, in Orange County, Vermont. The Project is located approximately 0.9 river miles from the Wells River’s confluence with the Connecticut River. Originally built in 1912, the presa is a concrete, gravity-type structure that is 90-feet-long by 26-feet-high with a south contrafuerte crest at 464.9 feet Datum vertical geodésico nacional (Vehículo motorizado nacional 29) and a north abutment crest at 464.4 feet NGVD 29. The aliviadero is 73.3 feet long by approximately 20 feet high and topped with a 5-foot-high and 73.3 foot-long pneumatic puerta de la cresta system. The spillway crest elevation is 458.9 feet NGVD 29, and the normal impoundment level is 463.9 feet NGVD 29 with the crest gate system inflated. The bypassed reach is approximately 590 feet long, and the impoundment is approximately 0.4 miles in length and covers a surface area of 11.4 acres at full pond, with 25 acre-feet of gross storage capacity. The average net cabeza at the project is 34 feet, and the normal tailwater elevation is 430.0 feet NGVD 29.

Additional project facilities include: a 5-foot-diameter, 435-foot-long underground steel compuerta; an intake structure; a central eléctrica located within the former Adams Paper Company mill building containing a single turbine-generator unit (Unit No. 1) rated at 0.315 MW and a minimum flow unit (Unit No. 2) located approximately 75 feet downstream of the dam rated at 0.05 MW; a tailrace; three 150-foot-long generator leads creating a 480 Volt (V), 3-phase, 150-foot-long underground transmission line connecting to three pole-mounted 167 kVA3 step-up transformadores; appurtenant facilities.


Historial de certificaciones

July 10, 2025: The Low Impact Hydropower Institute has received a complete application for Low Impact Certification of the Newbury Hydroelectric Project.  LIHI is seeking public comment on this application.  Specifically, we are interested in knowing whether you think the Project meets the LIHI Low Impact Certification Criteria, as revised in the 2nd Edition Handbook in effect at the time of initial application.  Please review the program and criteria in LIHI’s Revisión del manual 2.05 (the handbook version in effect at the time of initial draft application) and then review the Project’s application materials below.

Comentarios que están directamente relacionados con criterios específicos de LIHI (caudales, calidad del agua, paso de peces, etc.) serán de gran ayuda, pero se tendrán en cuenta todos los comentarios. Los comentarios pueden enviarse al Instituto por correo electrónico a comentarios@lowimpacthydro.org with “Newbury Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 68 Harrison Ave Ste 605, PMB 113938 Boston, Massachusetts 02111-1929.  Comments must be received on or before 5 pm Eastern time on September 8, 2025 Se considerarán todos los comentarios. Se publicarán en el sitio web y el solicitante tendrá la oportunidad de responder. También se publicarán todas las respuestas.


Archivos de certificación

Solicitud 2025


Documentos clave