LIHI Certificate #125 – Hunts Pond Dam Project, Massachusetts

項目名稱 Hunts Pond
理海證書編號 125
LIHI 證書期限
September 8, 2020 –
September 7, 2030
擁有者 Winchendon Hydroelectric LLC
狀態 麻薩諸塞州
地點 Located at river mile 38 on the Millers River  in Winchendon, MA.
裝置容量 0.1 MW
平均年發電量 480 MWH
設施類型 徑流
聯邦能源監管委員會 不。 P-8012, exempt 1985

The Hunts Pond Dam Project is located on the Millers River in the town of Winchendon, Massachusetts, in the middle of a series of dams on the Millers River. There are three dams upstream and six dams downstream. Whitney Dam (a non-powered ,) is approximately 0.5 miles upstream and Tannery Dam (P-8895) is approximately 0.3 miles downstream. The New Home Dam Project (LIHI #136) is located about 18 miles downstream. The Millers River is over 50 miles long, fed from tributaries in Rindge and New Ipswich, New Hampshire, Lake Monomonac, an artificial lake that straddles the border between Rindge, New Hampshire, and Winchendon, Massachusetts, and numerous ponds feeding the mainstem on its way to confluence with the Connecticut River. The project commenced operation in 1985 but went offline in February 1993 due to the owner at the time falling into bankruptcy. The project was sold in 1996. After repairing the existing units and updating the control system, the new owner brought the project back online.

The Hunts Pond Dam was built in 1936 and is a concrete structure184 feet long and 16 feet high. The concrete intake structure is approximately 25 feet long, operated with a steel headgate and 1-inch spaced trashracks. The open channel intake structure is located at the dam on the north side of the river. There is one steel gate 10.5 feet wide by 13.0 feet high at the entrance to the open channel intake structure. The head gate is manually operated and is used for maintenance purposes only. The open channel intake structure is approximately 25 feet long by 14 feet wide by 14.33 feet high. The wood frame 發電站 was built in 1985 and discharges directly back to the river. In 2013, a Federal Energy Regulatory Commission (FERC) 豁免 Amendment allowed for the installation of a new Kaplan turbine and 100 KW nameplate generator in 2015. No design changes to the dam or intake structures were required for the new Kaplan unit.

該項目運營於 徑流 mode and impounds a 120-acre reservoir. There is no bypassed reach. The elevation of Hunts Pond is controlled automatically by a 可程式邏輯控制器 (PLC) system, allowing the facility to operate in run-of-river mode and maintain the minimum flow requirements of 25 cfs (or inflow if less). The PLC enables the opening or closing of the intake wicket 蓋茲 automatically, regulating flow to the two cross flow turbines.

Waters within the project reach are designated as Category 5 waters requiring a TMDL and listed as impaired upstream of the project due to chronic aquatic toxicity and temperature. The impairments are likely due to a wastewater treatment plant upstream and the project is unlikely to affect water quality of the river.

American eel are the only migratory species present in the Millers River and are not present in the project vicinity due to downstream barriers which prevent passage. Historically, Atlantic salmon, American shad, blueback herring and sea lamprey may have migrated to the project area, but the downstream barriers now preclude access for the species. Resident fish species in the Millers River include stocked rainbow trout, brown trout, brook trout, smallmouth bass, rock bass, bluegill, pumpkinseed, redbreast sunfish, fallfish, and common shiner.

The project lands are limited to the project facilities. It has a very small footprint in an urbanized area with no lands of ecological significance. Threatened or endangered species potentially present in the project vicinity include the Northern long-eared bat though the project area does not provide any suitable habitat for the species.

No cultural or historic resources are present, but the nearby Mason and Parker Manufacturing Company is included in the Massachusetts Inventory of Historic Assets. This includes some of the project facilities, but the powerhouse and new intake structure were built in 1985, not yet old enough to be eligible for listing on the 國家歷史遺跡名錄 or the state inventory.

The project area is not safely accessible for recreational opportunities.


合規狀態

此證書包括以下設施特定條件:

Condition Satisfied in 2021.  條件一: By December 31, 2021 the facility Owner shall demonstrate FERC’s approval of the Stream Flow Compliance Plan dated 1/26/2016 and filed with FERC on May 1, 2017 by submitting to LIHI either a copy of a pre-existing FERC approval as requested in the Plan submittal, or a letter to FERC requesting approval, and the FERC approval issuance within 60 days of receiving it from FERC.

2024: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。

2023: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。

2022: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。

2021: There were no reported changes or compliance issues. The project remains in compliance based on the annual review.  For Condition 1, the project documented FERC’s approval of the compliance plan, thus satisfying the condition.


認證歷史

2022 年 1 月 1 日: 根據 2022 年 1 月 1 日發布的 LIHI 第二版認證手冊第 2.05 版,LIHI 證書期限已延長。

2021 年 6 月 22 日: The Low Impact Hydropower Institute has issued a final decision on the recertification of the Hunts Pond Dam Hydroelectric Project. The preliminary decision was announced on May 18, 2021 starting the 30-day appeal window. That window closed on June 17, 2021 and no appeals were filed. Therefore, the decision to recertify the project is now final. The new term for the project is September 8, 2020 through September 7, 2025.

May 18, 2021: The Low Impact Hydropower Institute (LIHI) has preliminarily approved the Hunts Pond Dam Project (LIHI #125) for a new 5-year term of Low Impact Certification. This decision is preliminary pending the 30-day appeal window. Only those who commented on the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the Project does not meet the LIHI criteria. Appeal requests can be submitted by email to 評論@lowimpactHydro.org with “Hunts Pond Dam Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 1167 Massachusetts Ave, Office 407, Arlington, MA 02476. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on June 17, 2021. The full application and reviewer’s report are available below. If no appeal requests are received and the decision becomes final, the Certification term for the Project will be February 11, 2021 through February 10, 2026.

February 23, 2021: The Low Impact Hydropower Institute (LIHI) has received a complete recertification application from Winchendon Hydroelectric, LLC for the Hunts Pond Dam Project. The complete application can be found below. LIHI is seeking comment on this application. Comments that are directly tied to specific LIHI criteria (flows, water quality, 魚道, etc.) will be most helpful, but all comments will be considered. Comments may be submitted to the Institute by e-mail at 評論@lowimpactHydro.org with “Hunts Pond Dam Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 1167 Massachusetts Avenue, Office 407, Arlington, MA 02476. Comments must be received at the Institute on or before 5 pm Eastern time on April 24, 2021 to be considered. 所有評論都將發佈到網站上,申請人將有機會回應。任何回覆也會公佈。

December 24, 2015 – LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board and a full review of the Application Reviewer’s report and all public comments and additional materials provided by the Applicant, has certified that the Hunts Pond Dam Hydroelectric Project (FERC No. P-8012) satisfies the LIHI Certification Criteria.  A Preliminary Decision was announced on November 25, 2015, and a 30-day appeal period was open through December 24, 2015. No requests for appeal were received. This Certification Decision includes one facility-specific condition, as follows:

  • Condition satisfied 2016: Within 30 days of LIHI Certification approval, the facility owner shall provide a letter to LIHI that commits to upstream and downstream passage protections for American Eel if and when such fish passage mitigation is determined to be necessary by the MDFW and/or USFWS.

The effective certification date for the Hunts Pond Dam Project is September 8, 2015 for a five (5) year term, which will expire on September 5, 2020.

September 8, 2015 – On September 8, 2015, the Low Impact Hydropower Institute (LIHI) received a complete application from Winchendon Hydroelectric LLC for the Low Impact Certification of the Hunts Pond Dam Project, FERC P-8012, located on the Millers River in Winchendon, Massachusetts.


認證文件

2021 Recertification

2015年認證


關鍵文件