Solicitud pendiente - Proyecto Skelton, Maine

Nombre del proyecto Skelton
Certificado LIHI No.
pending #203
Plazo del certificado LIHI
N / A
Dueño Brookfield White Pine Hydro, LLC
Estado Maine
Ubicación Milla fluvial 16 – Río Saco
Capacidad instalada 21,6 MW
Generación media anual 108.204 MWh
Tipo de instalación Modificado estacionalmente de pasada
Comisión Federal de Comercio No. P-2527. Licencia expedida en 1988, vence el 31/01/2038.

El Proyecto Skelton (FERC No. 2527) está ubicado en el río Saco en el condado de York, Maine, aproximadamente 11,1 millas fluviales por encima del nivel del mar. cabezade marea en Saco y a 16 millas fluviales desde la desembocadura del río en Camp Ellis/Hills Beach. El Proyecto presa y central eléctrica Se ubican en las localidades de Buxton y Dayton, Maine. El embalse se encuentra en las localidades de Buxton, Dayton y Hollis. El proyecto es la segunda presa en el río Saco y uno de los siete proyectos hidroeléctricos ubicados en el cauce principal del río.

El proyecto consiste en un túnel de hormigón de gravedad y tierra de 1.695 pies de largo. presa de terraplén Está rematada con una calzada y se construyó originalmente entre 1947 y 1949. La presa consta de: (1) una sección de terraplén de tierra, de 365 metros de largo por 18 metros de alto, con una elevación de coronación de 43 metros (USGS); (2) un mamparo oeste y aliviadero Sección de la puerta, de unos 170 pies de largo por 75 pies de alto, rematada con cuatro Tainter puertas, cada uno de 32,5 pies de ancho por 20 pies de alto, con una elevación de umbral de 108,0 pies (USGS); (3) una estructura de entrada, de 107 pies de largo por 146 pies de ancho, tiene dos aberturas de entrada, protegidas por rejillas de basura de barras de acero de 5/8 de pulgada en aberturas de 3 pulgadas; (4) una escala de peces y sección de compuerta, de unos 30 pies de largo; (5) un mamparo este y sección de compuerta de aliviadero, de unos 188 pies de largo por 75 pies de alto, rematado con cuatro compuertas Tainter, cada una de 32,5 pies de ancho por 20 pies de alto, con una elevación de umbral de 108,0 pies (USGS); y (6) un muro de contención de hormigón, que atraviesa el terraplén occidental de unos 763 pies de largo, con una elevación de cresta de 143,0 pies (USGS).

La presa forma un embalse ribereño de aproximadamente 4,5 km de largo y hasta 300 m de ancho. El embalse incluye aproximadamente 3,4 km del arroyo Cook en su confluencia con el río Saco. El límite del proyecto se extiende aguas arriba hasta el cauce del Proyecto Bar Mills (FERC n.° 2194) y aguas abajo hasta el embalse. Proyecto de Cataratas, LIHI #169Más arriba se encuentra el Proyecto Bonny Eagle (LIHI #182).

La central eléctrica es parte integral de la presa, que crea un embalse de 488 acres. La central eléctrica contiene dos unidades de turbina/generador Kaplan de eje vertical con una capacidad total de 21,6 MW. El proyecto opera como una instalación de pasada con modificación estacional. La operación del proyecto se gestiona en conjunto con el flujo y almacenamiento de agua de los proyectos aguas arriba, de conformidad con el Acuerdo de Caudal del Río Saco de 1997, como se detalla a continuación:

  • Del 1 de abril al 30 de junio, el proyecto funciona en modo de pasada con solo 1 pie de fluctuación permitida con respecto al nivel normal del estanque lleno.
  • Del 1 de julio al 30 de septiembre, el caudal mínimo aumenta a 400 pies cúbicos por segundo (cfs) cuando la entrada supera los 400 pies cúbicos por segundo. Cuando la entrada cae por debajo de 400 pies cúbicos por segundo, el proyecto continúa liberando 400 pies cúbicos por segundo extrayendo agua del embalse, con la reducción del nivel del embalse limitada a 4 pies o menos desde la elevación máxima del estanque. Una vez que la elevación del embalse cae 4 pies por debajo de la elevación máxima del estanque, el caudal de salida es igual a la entrada.
  • Del 1 de octubre al 15 de noviembre (sujeto al período alternativo de 6 semanas aprobado por la agencia), el caudal mínimo aumenta a 600 cfs o entrada, lo que sea menor.
  • Del 15 de noviembre al 31 de marzo, el caudal mínimo es de 400 pies cúbicos por segundo (cfs) cuando la entrada es superior a 400 pies cúbicos por segundo. Cuando la entrada cae por debajo de 400 pies cúbicos por segundo, el proyecto continúa liberando 400 pies cúbicos por segundo extrayendo agua del embalse, con la reducción del nivel del embalse limitada a 4 pies o menos desde la elevación máxima del estanque. Una vez que la elevación del embalse cae 4 pies por debajo de la elevación máxima del estanque, el caudal de salida es igual a la entrada.

The Saco River in the project vicinity is a Class A water, suitable for the designated uses of drinking water after disinfection; fishing; agriculture; recreation in and on the water; industrial process and cooling water supply; hydroelectric power generation, and as habitat for fish and other aquatic life. The river in the project vicinity is not listed as impaired. Water quality monitoring had been conducted and Maine DEP confirmed that the project is in compliance with it water quality certification.

The project is equipped with upstream and downstream paso de peces facilities installed in 2001. Upstream fish passage is provided by a fish lift located on the south side of the powerhouse, and consists of an attraction water system, a fish crowder system, a hopper/elevator, and truck and trap holding systems. Downstream fish passage is provided by a concrete log sluice centrally located in the dam equipped with a 5-foot by 5-foot slide gate located at the headworks. The project also has an upstream eel passage that was first operational in 2013. It includes a roughened cement attraction water flow area on the East side of the Skelton spillway leading the juvenile eels to a three-foot long EnkaMat ramp and into an elevator tank with approximately 50-gallon capacity.

Lands around the project are primarily forested or under agricultural use. There are no lands of ecological significance. De pasada operations and limited impoundment fluctuations serve to limit erosion and serves to benefit existing humedales and wildlife.

Threatened or endangered species that may be present include small whorled pogonia and Blanding’s turtle (state engandered). Other species proposed for listing include tri-colored bat and monarch butterfly. Other bats may also be present including the state endangered little brown bat and Northern long-eared bat (also federally endangered), and the state threatened Eastern small-footed bat. Bald eagles and other migratory birds may also be present on a periodic basis. Four rare plant species adjacent to the project boundary:  hollow joe-pye weed; spotted wintergreen; hairy wood brome-grass; and American chestnut. Project operations are unlikely to adversely affect any protected species because vegetation removal within 250 feet of any waterway is regulated by the Maine DEP Shoreline Zoning Act and the project does not typically need to cut trees or engage in more impactful land-based activities.

Four archaeological sites exist in the project area that are eligible for inclusion in the Registro Nacional de Lugares Históricos.  The FERC License requires  implementation of the 1993 Programmatic Agreement to protect these resources. A review of the annual reports required by Article 415 for the previous 10 years did not indicate any cultural or historic resource issues at the Project.

Recreational amenities at the project include a boat launch area on the western shore just upstream of the dam that additionally serves as a portage take-out, and a portage trail with a put-in on the western shore downstream of the tailrace. Recreational facilities are available free of charge.


Historial de certificaciones

July 1, 2025: The Low Impact Hydropower Institute (LIHI) has preliminarily approved Low Impact Certification for the Skelton Hydroelectric Project, (pending LIHI #203). The full application and reviewer’s report are available below.

Esta decisión es preliminar, a la espera del plazo de apelación de 30 días. Solo quienes comentaron sobre las solicitudes iniciales durante el plazo de 60 días pueden presentar una apelación. Dicha apelación debe incluir una explicación de por qué los Proyectos no cumplen con los criterios de LIHI. Las solicitudes de apelación pueden enviarse por correo electrónico a mailto:comments@lowimpacthydro.org with “Skelton Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 68 Harrison Ave Ste 605, PMB 113938 Boston, Massachusetts 02111-1929. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on July 31, 2025. If no appeal requests are received the certification term will be March 5, 2025 through March 4, 2035.

6 de marzo de 2025: El Instituto de Energía Hidroeléctrica de Bajo Impacto (LIHI) ha recibido una solicitud completa para la Certificación de Bajo Impacto del Proyecto Hidroeléctrico Skelton. LIHI solicita comentarios públicos sobre esta solicitud. En concreto, nos interesa saber si considera que el Proyecto cumple con los Criterios de Certificación de Bajo Impacto de LIHI, revisados en la 2.ª edición del Manual vigente al momento de la solicitud inicial. Por favor, revise el programa y los criterios en el sitio web de LIHI. Revisión del manual 2.05y luego revise los materiales de solicitud del Proyecto a continuación.

Los comentarios que estén directamente relacionados con criterios específicos del LIHI (caudales, calidad del agua, paso de peces, etc.) serán de gran ayuda, pero se tendrán en cuenta todos los comentarios. Los comentarios pueden enviarse al Instituto por correo electrónico a comentarios@lowimpacthydro.org con “Comentarios del Proyecto Skelton” en la línea de asunto, o por correo dirigido al Low Impact Hydropower Institute, 68 Harrison Ave Ste 605, PMB 113938 Boston, Massachusetts 02111-1929.  Los comentarios deben recibirse antes de las 5 p. m., hora del Este, del 5 de mayo de 2025. Se considerarán todos los comentarios. Se publicarán en el sitio web y el solicitante tendrá la oportunidad de responder. También se publicarán todas las respuestas.


Archivos de certificación

Solicitud 2025


Documentos clave