項目名稱 | Upper La Chute |
理海證書編號 | 185 |
LIHI 證書期限 | 2021 年 8 月 5 日 – 2031 年 8 月 4 日 |
擁有者 | La Chute Hydro Company, LLC,LS Power/ Patriot Hydro, LLC 的子公司 |
狀態 | 紐約 |
地點 | Located at river mile 3.3 on the La Chute River in Ticonderoga, Essex County, NY |
裝置容量 | 4.9 MW |
平均年發電量 | 19,000 MWh |
設施類型 | 徑流 |
聯邦能源監管委員會 不。 | P-5760 exempt 1984 |
The Upper La Chute Project and the Lower La Chute Hydroelectric Project (LIHI #186) 均位於紐約州艾塞克斯郡提康德羅加村的拉舒特河畔。拉舒特河從喬治湖流向尚普蘭湖,長約 2.5 英里。
The Upper La Chute Project consists of three dams, Mill A 壩 (Lake George Outlet dam, the control structure for the water surface level of Lake George into the La Chute River), Mill B dam, and Mill C dam. Upper La Chute utilizes the waters of Lake George, a 44 square mile recreational lake in upstate New York, as the 源頭 for the project. The releases from Lake George are set by New York State statute and guidelines and are regulated by the New York State Department of Environmental Conservation (NYSDEC). Flows from Lake George are conveyed 2,300 feet downstream by a steel 壓力水管 9 feet in diameter to a 發電站 located near Mill C. The dam forms a bypassed reach approximately 1 mile long. The powerhouse has a single turbine-generator unit rated at 4,900 kilowatts.
The Upper La Chute project operates in 徑流 mode and inflows are dictated by flow releases from Lake George. More specifically, operations are detailed in the 1992 Lake George 壩 Operating Guidelines for the Upper La Chute Hydroelectric Project, which provides other regulations for the stewardship of the water resources at Lake George and at the project. A continuous minimum flow of 30 cfs in the bypassed reach is provided to support resident aquatic biota.
Waters within the project reach are designated as Class AA-S(TS) at Lake George, Class C(TS) in the bypassed reach, and Class C in the tailwater reach. Lake George is listed as impaired for silt and sediment pollution due to urban and storm runoff as well as erosion. The Lake George Watershed Association has taken many steps to help prevent polluted flows from entering the lake. Class AA waters are best used for drinking water, primary or 二次接觸娛樂, and fishing. Class C waters are best used for fishing. The application of (TS) indicates that the classifications are supportive of trout populations.
The La Chute River in the project vicinity supports a mix of warmwater and coldwater fish species. Of these, several migratory species are found at the project including blueback herring, alewife, American eel, lake sturgeon, landlocked Atlantic salmon, and sea lamprey. Atlantic salmon are maintained via stocking and American eel are similarly supported via stocking. Blueback herring, alewife, and sea lamprey are considered non-native or invasive and thus pose a threat to native species, especially trout and salmon. Passage is not desirable for these species as they could negatively impact native fish populations in Lake George. Downstream passage is provided via a downstream bypass which includes a buried pipe with an underground sluice that carry fish to the bypass reach. Downstream passage is also provided through the minimum flow weir at Upper La Chute.
該項目土地面積近 500 英畝,涵蓋上拉舒特 (Upper La Chute) 計畫和下拉舒特 (Lower La Chute) 計畫。工程附近的海岸線是落葉林和常綠林的混合區,其中有種植有觀賞草的住宅和商業地產。一些農田和 濕地 are also found in the area. The 1992 Lake George Dam Operating Guidelines for the Upper La Chute Hydroelectric Project provides specific provisions regarding the management of water levels in the Lake George watershed.
計畫附近可能存在的受威脅或瀕危物種包括印第安納蝙蝠和北長耳蝙蝠。在項目附近沒有發現任何兩種物種的關鍵棲息地。其他列出的植物和鳥類物種被列為可能存在,儘管該項目未在可能發現這些物種的地區開展或對其產生影響。
Consultation with the State Historic Preservation Office concluded that project operations do not have an adverse impact on historical or cultural resources in the area.
Recreational resources at the project include fishing, boating, and camping access at the Upper impoundment. There is also fishing access in the bypass reach. Public access is provided free of charge.
合規狀態
目前證書中沒有針對設施的具體條件
2024: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。
2023: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。
2022: 未發現重大變更或合規問題。根據年度審查,該項目仍符合規定。
2021: 目前證書的年度報告尚未生效。
認證歷史
2022 年 1 月 1 日: 根據 2022 年 1 月 1 日發布的 LIHI 第二版認證手冊第 2.05 版,LIHI 證書期限已延長。
2021 年 12 月 14 日: The Low Impact Hydropower Institute has issued a final decision on the certification of the Upper La Chute Project. The 30-day appeal window closed on December 4, 2021 and no appeals were filed. Therefore, the decision to certify the project is now final. The new term is August 5, 2021 through August 4, 2026.
2021年11月4日: 低影響水力發電研究所 (LIHI) 已初步批准對上拉楚特計畫和下拉楚特計畫進行為期 5 年的低影響認證。該決定是初步決定,需等待 30 天的上訴期。只有在 60 天的評論期內對初始申請發表評論的人才有資格提出上訴。此類上訴需要包括有關該項目為何不符合 LIHI 標準的解釋。申訴請求可以透過電子郵件發送至 評論@lowimpactHydro.org 主題行為“Upper and Lower La Chute Projects”,或郵寄至 Low Impact Hydropower Institute,地址為 1167 Massachusetts Ave, Office 407, Arlington, MA 02476。所有請求都將發佈在網站上。申請人將有機會回應,任何回應也將公佈。 請求必須在 2021 年 12 月 4 日東部時間下午 5 點之前收到。 完整的申請和審核員報告如下。如果沒有收到上訴請求並且決定成為最終決定,則每個項目的認證期限為 2021 年 8 月 5 日至 2026 年 8 月 4 日。
2021 年 8 月 5 日:低影響水力發電研究所已收到拉舒特上下游計畫低影響認證的完整申請。 LIHI 正在就此申請徵求公眾意見。具體來說,我們想知道您是否認為該項目符合第二版手冊中修訂的 LIHI 低影響認證標準。請查看 LIHI 修訂版中的計劃和標準 手冊 然後查看下面該項目的申請資料。與特定 LIHI 標準(流量、水質、 魚道等等)將非常有幫助,但所有評論都會被考慮。意見可以透過電子郵件提交給研究所 評論@lowimpactHydro.org 主題行為“La Chute 計畫評論”,或郵寄至低影響水力發電研究所,地址:1167 Massachusetts Avenue, Arlington, MA 02476。 評論必須在東部時間下午 5 點或之前收到 2021 年 10 月 4 日 有待考慮。 所有評論都將發佈到網站上,申請人將有機會回應。任何回覆也會公佈。
認證文件
2021 年認證