LIHI Certificate #45 - Farmers Irrigation District Hydroelectric Project, Oregon
Farmers Irrigation District Hydroelectric Projects are located on canals discharging to the main stem of the Hood River near the ColumbiaRiver Gorge about 60 miles west of Portland, Oregon. The project including penstocks and powerhouses, were constructed in the mid-1980s to produce renewable energy for the Bonneville Power grid and provide revenue to the District to be used for water conservation, stream restoration, and fish screen projects. The project consists of two powerhouses. The upper powerhouse (No. 3) contains a 1.8 MW generator with a horizontal axis Pelton turbine; the lower powerhouse (No. 2) contains two generators – 1.0 MW and 2.0 MW – driven by horizontal axis Francis turbines. Each plant has its own switchgear, and electricity flows from both plants to a single substation, which is connected directly to the Bonneville grid.
The projects are run-of-river, and no dams are associated with the project's six water diversion systems. Water flows to the upper powerhouse (Plant No. 3) forebay through the 10-mile long Lowline canal and pipe system; water to the lower plant forebay flows through the 5-mile long Farmers canal and pipe system. The project has no reservoir storage other than the forebay, canal, and pipe systems. A 5-mile long, 36-inch diameter penstock provides water to the upper turbine, and a 2-mile long, 48-inch diameter penstock conveys water to the lower turbines. Water from the upper plant also flows through the lower plant. Farmers Irrigation District owns the project facilities and holds easements for the canals, pipes, forebays, penstocks, and transmission lines.
The District diverts its project water through self-cleaning, horizontal fish screens, a technology developed by the District that allows fish to pass through the diversion systems without harm. The District maintains year-round minimum flows in Green Point Creek, a premier anadromous fish-bearing stream that is one of the sources of water for the upper plant. Plant No. 3 is operated at reduced capacity if Green Point Creek flow drops below the minimum, and the plant typically does not run at all during the summer months. In the 1990s, the Hood River was listed for threatened salmon and steelhead, and the Hood River was also placed on the Clean Water Act 303d list for water temperature. In the response to these listings, in a concerted effort to ensure that the District's power plants are low impact, the District works with the Oregon Department of Fish and Wildlife, Oregon Department of Environmental Quality, and the Confederated Tribes of Warm Springs to alter plant operation to enhance Hood River mainstem in-stream flow during the summer months and ensure that the District's project does not increase water temperature.
Nom du projet | District d'irrigation des agriculteurs |
Numéro de certificat LIHI | 45 |
Durée du certificat LIHI | March 25, 2014 - March 25, 2019 Extended to June 30, 2020 |
Propriétaire | District d'irrigation des agriculteurs |
État | Oregon |
Emplacement | Située au large du cours principal de la rivière Hood, près des gorges du fleuve Columbia, à environ 60 miles à l'ouest de Portland, dans l'Oregon. L'usine n° 2 se déverse dans la rivière Hood au mile 4,5 |
Capacité installée | 4,8 MW |
Génération annuelle moyenne | 22,000 MWh |
Type d'établissement | Conduit |
Numéro FERC | FID No. 2 P-7532 exempt 1984 FID No. 3 P-6801 exempt 1983 |
Historique des certifications
18 juin 2020 : The Low Impact Hydropower Institute (LIHI) has preliminarily approved the Farmers Irrigation District Project (LIHI #45) for a new 5-year term of Low Impact Certification. The Certificate includes the following condition:Condition 1 : The facility Owner shall continue to operate the Project in accordance with the 2019 Memorandum of Agreement (MOA) with ODFW and ODEQ and provide status updates to LIHI in annual compliance statements. Updates should specify if operations are modified as a result of the adaptive management program, or if the MOA is revised during the LIHI term.
Cette décision est préliminaire en attendant la période d'appel de 30 jours. Seuls ceux qui ont commenté la demande initiale pendant la période de commentaires de 60 jours sont éligibles pour déposer un appel. Un tel appel doit inclure une explication sur la raison pour laquelle le projet ne répond pas aux critères du LIHI. Les demandes d'appel peuvent être soumises par courrier électronique à commentaires@lowimpacthydro.org with "Farmers Irrigation District Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Les demandes doivent être reçues avant 17 heures, heure de l'Est, le 18 juillet 2020.. The full application and reviewer's report are available below.
If no appeal requests are received and the decision becomes final, the Certification term for the Project will be March 25, 2019 through March 24, 2029.31 mars 2020 : Le Low Impact Hydropower Institute a reçu une demande complète de recertification à faible impact du projet hydroélectrique du district d'irrigation des agriculteurs. Le LIHI sollicite les commentaires du public sur cette demande. Plus précisément, nous souhaitons savoir si vous pensez que le projet répond aux critères de certification à faible impact du LIHI, tels que révisés dans le manuel de 2e édition. Veuillez consulter le programme et les critères dans le manuel révisé du LIHI Manuel et consultez ensuite les documents de candidature du projet ci-dessous.
Les commentaires directement liés à des critères spécifiques du LIHI (débits, qualité de l'eau, passage des poissons, etc.) seront les plus utiles, mais tous les commentaires seront pris en compte. Les commentaires peuvent être envoyés à l'Institut par courrier électronique à l'adresse commentaires@lowimpacthydro.org avec « Commentaires sur le projet du district d'irrigation des agriculteurs » dans la ligne d'objet, ou par courrier adressé au Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420. Les commentaires doivent être reçus au plus tard à 17 heures, heure de l'Est, le 30 mai 2020. à prendre en considération. Tous les commentaires seront publiés sur le site Web et le candidat aura la possibilité d'y répondre. Toute réponse sera également publiée.
22 avril 2014 : Les projets hydroélectriques du district d'irrigation des agriculteurs ont été certifiés pour un deuxième mandat de cinq ans, à compter du 25 mars 2014 et expirant le 25 mars 2019.
27 janvier 2014 : Le Low Impact Hydropower Institute a reçu une demande de certification du Farmers Irrigation District pour un second mandat. Les documents de candidature sont disponibles dans la section « Fichiers » ci-dessous.
20 novembre 2009 : Le projet de district d'irrigation des agriculteurs a été certifié à faible impact pour une durée de cinq ans, à compter du 25 mars 2009 et expirant le 25 mars 2014.
25 mars 2009 : Le Farmers Irrigation District a déposé une demande de certification pour son projet hydroélectrique de petite taille. Une période de commentaires publics restera ouverte pendant 60 jours, jusqu'au 25 mai 2009.
Fichiers:
Recertification 2020
- Farmers Irrigation District Review Report 2020-06-17
- FID Hydro Project (#45) LIHI recertification application
Recertification 2014
- FIDQuestionnaire_Nov2013
- 2014-04-17 Recertification Review_FID
- FIDThermalImpactReportNov2013
- FIDSustainabilityPlanNov2013
- FID Hydro Project (#45) LIHI recertification application