Final Decision – Certification of the North Twin Project, LIHI #183
septembre 7, 2021September 7, 2021: The Low Impact Hydropower Institute has issued a final decision on the recertification of the Otter Creek Project located on Otter Creek in Vermont. The 30-day appeal window closed on September 2, 2021 and no appeals were filed. Therefore, the decision to certify the project is now final. The certificate term is January 7, 2021 through January 6, 2026. There are no conditions attached to the Certificate.
Décision préliminaire – Certification du projet de barrage Wells, en attente LIHI #203, WA
En savoir plus