Final Decision – Certification of the Sherman Island Project, LIHI #177
2020 年 12 月 21 日
緬因州邦尼伊格爾計畫 - 已收到完整申請
2021年1月11日January 6, 2021: The Low Impact Hydropower Institute (LIHI) has preliminarily approved recertification of the West Branch St. Regis Project (LIHI #27) for a new 5-year term of Low Impact Certification. The Project is located on the West Branch of the St. Regis River in New York. The Certification includes the following condition:
條件一: If maintenance activities along the Parishville 發電站 roadway and pipeline right-of-way are significantly altered, such as widespread herbicide application, widening of the roadway or placement of fill adjacent to the roadway where the Fernald’s sedge plant has been observed, the facility Owner shall consult with the NYSDEC regarding potential impacts to the species. The Owner shall report on any such activities in the LIHI annual compliance submittals including results of consultation and evidence of implementation of any requirements mandated by the NYSDEC to protect this species if it is found onsite.
該決定是初步決定,需等待 30 天的上訴期。只有在 60 天的評論期內對初始申請發表評論的人才有資格提出上訴。此類上訴需要包括有關該項目為何不符合 LIHI 標準的解釋。申訴請求可以透過電子郵件發送至 評論@lowimpactHydro.org with “West Branch St. Regis Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on February 5, 2021. 完整的申請和審稿人報告可供使用 這裡。
If no appeal requests are received and the decision becomes final, the Certification term for the Project will be September 14, 2020 through September 13, 2025.
北安普誇項目,LIHI #69 OR – 已收到完整的重新認證申請
閱讀更多