LIHI Certificate #76 - West Dudley Project, Massachusetts

項目名稱 West Dudley
理海證書編號 76
LIHI 證書期限
April 7, 2020 – April 6, 2030
擁有者 West Dudley Hydro Bros LLC
狀態 麻薩諸塞州
地點 Located at approximate river mile 50 on the Quinebaug River in Dudley, Massachusetts.
裝置容量 0.310 MW
平均年發電量 611 MWh
設施類型 徑流
聯邦能源監管委員會 不。 P-7254 exempt 1983

The West Dudley Project is located on the Quinebaug River in the town of Dudley, Massachusetts. Construction of the Quinebaug River Pond (also known as the Rhode Island Cardboard Company Dam) was completed in 1919. The project is located downstream of the Westville Lake, Old Sturbridge village, and East Brimfield dams. Downstream of the project are West Thompson Dam, MSC Hydro, Putnam Hydro (LIHI #3), Cargill Falls Dam, Rogers Dam, Quinebaug part of LIHI #166), Aspinook, and Tunnel Dam.

該項目包括 consisting of two sections, 55 feet in length and 144 feet in length.

The brick-and-masonry 發電站 contains three turbine generators. Unit 1 is a modified Medsker brand turbine with a belt-driven induction motor. It is a fixed-blade Kaplan style that develops 95 kW of power. Unit 2 is also a modified Medsker brand turbine with a belt-driven induction motor. Itis a fixed-blade Kaplan style which develops 120 kW of power. Unit 3 is a Flygt brand submersible unit with a direct-coupled planetary gearbox and induction generator. Total capacity is 0.31 MW. The powerhouse is flanked by two 溢洪道 sections, 55 feet and 114 feet in length and 17 feet high
on average. The 溢洪道 carry 閃光板 four feet in height. There is no bypass reach.

該項目運營於 徑流 mode and impounds a 31-acre reservoir. The project provides a continuous minimum flow of 76 cfs to ensure protection of aquatic resources in the Quinebaug River. The flow regime was developed based on recommendation by the US Fish and Wildlife Service (USFWS). A flow monitoring plan was developed and implemented in 2012 as a result of initial LIHI certification. The plan was developed with and approved by USFWS, Massachusetts Division of Fisheries and Wildlife (MDFW), and the Massachusetts Department of Environmental Protection (MDEP).

Waters within the project reach are designated as Class B, best suited for irrigation/agricultural use and industrial cooling/processes. The reach is also impaired for dissolved oxygen, E. coli, fecal coliform, and other nutrients. MDEP has confirmed that the project does not contribute to these impairments and are likely due to the wastewater treatment plant upstream of the project.

Several dams downstream of the project preclude access for migratory 溯河洄游魚類 species. American eel is present in the Quinebaug River upstream and downstream of the project, indicating that the species is able to pass upstream on their own. The project shuts down operations and spills inflow on nights from August 15 through November 15 whenever a rain event of 0.25-inch or more occurs in a 24-hour period, or whenever there is a 50% increase in inflow over the previous three-day average. These actions help provide downstream passage for migrating American eels.

The project lands consist of 29 acres. Industrial, residential and undeveloped lands are all found in the project area. Some of the undeveloped land primarily on the west side of the river, close as it is to intensive industrial and commercial use, provides some wildlife habitat. Undeveloped lands include a number of wooded areas some of which are seasonally flooded. The remainder of the area consists of low-density residential and small industrial development. Run-of-river operations ensure protection of the shoreline.

Threatened or endangered species potentially present in the project vicinity include the Northern long-eared bat, large bracted tick-trefoil, and shining wedgegrass. Due to the project area’s industrial and commercial land use, it is highly unlikely that any of the listed species could find suitable habitat within the project boundary.

Consultation with the Massachusetts State Historic Preservation Office concluded that no cultural or historic resources exist in the project area and operations would not adversely affect any such resources.

Recreational resources at the project include a boat launch in the impoundment, as well as a canoe portage, take-out, and put-in. Minimal hiking and boating occur in the project area. Public access is provided free of charge.


合規狀態

The Certification includes the following condition:

條件一: The facility Owner will continue to voluntarily provide interim downstream eel passage until such time as the voluntary permanent downstream passage measures are implemented. The facility Owner shall provide LIHI with an annual update on the schedule for permanent passage implementation and, upon completion, shall provide evidence that the installation is functional and acceptable to resource agencies.

2024: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.  For Condition 1, the project reported no change in status and interim measures continue.

2023: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.  For Condition 1, the project reported no change in status and interim measures continue.

2022: No material changes or compliance issues were identified. The project remains in compliance based on the annual review.  For Condition 1, the project reported no change in status and interim measures continue. The project changed ownership in 2021.

2021: There were no reported changes or compliance issues. The project remains in compliance based on the annual review. For Condition 1, the project reported that continued interim downstream eel passage is being provided by nightly shutdowns in rainy weather between August 15 and November 15 in accordance with Condition 1 in the prior certification (see Certification History below).

2020: 目前證書的年度報告尚未生效。


認證歷史

2022 年 1 月 1 日: 根據 2022 年 1 月 1 日發布的 LIHI 第二版認證手冊第 2.05 版,LIHI 證書期限已延長。

2020年11月17日: The decision to recertify the West Dudley Project became final after the close of the appeals period on November 15, 2020 with no appeals filed. The Certification term is from April 7, 2020 – April 6, 2025.

October 16, 2020: The Low Impact Hydropower Institute (LIHI) has preliminarily approved recertification of the West Dudley Project (LIHI #76) for a new 5-year term of Low Impact Certification. The Project is located on the Quinebaug River in Massachusetts.

該決定是初步決定,需等待 30 天的上訴期。只有在 60 天的評論期內對初始申請發表評論的人才有資格提出上訴。此類上訴需要包括有關該項目為何不符合 LIHI 標準的解釋。申訴請求可以透過電子郵件發送至 評論@lowimpactHydro.org with “West Dudley Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 6, Lexington, MA 02420. All requests will be posted to the website. The applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on November 15, 2020. The full application and reviewer’s report are available below. If no appeal requests are received and the decision becomes final, the Certification term for the Project will be April 7, 2020 through April 6, 2025.

August 12, 2020:The Low Impact Hydropower Institute has received a complete application for Low Impact recertification of the West Dudley Hydroelectric Project. The complete application can be found below.

LIHI is seeking public comment on this application. Comments that are directly tied to specific LIHI criteria (flows, water quality, 魚道, etc.) will be most helpful, but all comments will be considered. Comments may be submitted to the Institute by e-mail at comments@lowimpacthydro.org with “West Dudley Project Comments” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Avenue, Suite 6, Lexington, MA 02420. Comments must be received on or before 5 pm Eastern time on October 11, 2020 to be considered. 所有評論都將發佈到網站上,申請人將有機會回應。任何回覆也會公佈。

May 6, 2016: LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board, has certified that the West Dudley Hydroelectric Project (FERC No. P-7254) satisfies the LIHI Certification Criteria. A Preliminary Decision was announced on April 6, 2016, and a 30-day appeal period was open through May 6, 2016. No requests for appeal were received. This Certification Decision includes one facility-specific condition, as follows:

  • 條件一:The Owner shall continue to provide interim safe, timely, and effective downstream passage for American eel on an annual basis during the period August 15 through November 15.  The Owner shall cease generating from dusk to dawn during that period whenever either of the following occurs: 1) a rain event of 0.25 inch or more in a 24-hour period, or 2) a 50% increase in flow over the previous three-day average flow (e.g., if a substantial water release occurs from an upstream reservoir). The generation shutdowns shall continue for 72 hours (i.e., three nights). The Owner shall keep a log during this period, showing hourly precipitation and generation information, and provide it to LIHI, the U.S. Fish and Wildlife Service and the Massachusetts Division of Fisheries and Wildlife by December 31 annually until permanent measures are in place. In the event that either the U.S. Fish and Wildlife Service or the Massachusetts Division of Fisheries and Wildlife determine that the above-described interim downstream passage measure is not providing safe, timely and effective passage for out-migrating eels, the Owner shall implement other reasonable interim measures as requested by these agencies.  The Owner may also propose alternative eel passage measures for consideration if such measures have a strong technical and scientific basis.  During the term of this certification, should a resource agency request implementation of permanent downstream passage or upstream passage at the Facility, the Owner shall notify LIHI within 14 days of that request and provide LIHI with a copy of the request and the Owner’s response.

The effective certification date for the West Dudley is April 7, 2015 for a five (5) year term, which will expire on April 7, 2020.

2015年12月4日: On December 4, 2015, the Low Impact Hydropower Institute received a complete application for a new term of Low Impact Certification for the West Dudley Hydroelectric project.  The application materials can be found in the Files section below.

The public comment period for this application closed on February 8, 2016.

September 22, 2011: The West Dudley Hydroelectric Project has been certified as low impact for a five year term, effective April 7, 2011 and expiring April 7, 2016.

April 7, 2011: West Dudley Hydro, LLC has submitted an application for the certification of the West Dudley Project. The public comment period will remain open for 60 days.


認證文件

2020 年重新認證

2015 年重新認證

2011年認證


關鍵文件