Lexington MA (September 6, 2018): On September 4, 2018, the Low Impact Hydropower Institute (LIHI) preliminarily approved the Passumpsic Hydroelectric Project for a new 5-year term of Low Impact Certification, with the following conditions:

  • Condition 1: The Owner shall provide LIHI with evidence that FERC has approved the Revised Flow Management Plan (filed by GMP on April 25th, 2018) within 60 days from the date of issuance of that approval.
  • Condition 2: The Owner will provide LIHI with evidence that FERC has approved the Downstream Fish Passage and Operations and Maintenance Plan (filed by GMP on April 25th, 2018) within 60 days from the date of issuance of that approval.  If FERC issues new terms and conditions, the LIHI Certification is subject to amendment to incorporate such terms and conditions.
  • Condition 3: The Owner shall provide a LIHI with a copy of the final report to FERC demonstrating the completion of the portage pathway improvements within 60 days of filing that report with FERC.

This decision is preliminary pending the 30-day appeal window. Only those who commented in the initial application during the 60-day comment period are eligible to file an appeal. Such appeal needs to include an explanation as to how the projects do not meet the LIHI criteria. Appeal requests can be submitted by email to comments@lowimpacthydro.org with “Passumpsic Hydroelectric Project” in the subject line, or by mail addressed to the Low Impact Hydropower Institute, 329 Massachusetts Ave, Suite 2, Lexington, MA 02420. All requests will be posted to the website and the applicant will have an opportunity to respond and any response will also be posted. Requests must be received by 5 pm Eastern time on October 6, 2018.  The full application and reviewers report are available HERE.

If no appeal requests are received and the decision becomes final, the new term for