The School Street Project includes a 1,280-foot-long, 16-foot-high masonry gravity overflow-type dam that impounds a 100-acre reservoir with a normal maximum water surface elevation of 156.1 feet U.S. Geological Survey (USGS) datum, and an adjacent 375-foot-long, 18-foot-high ice fender. The 206-foot-long upper gatehouse, with nine timber slide gates and three steel Taintor gates, controls flows to a 4,400-foot- long, 150-foot-wide power canal located along the west bank of the river, conveying water to a 152-foot-long lower gatehouse with five steel headgates equipped with 3.1- inch clear bar spaced trashracks, leading to five 190-foot-long penstocks, four 11-foot- diameter, and one 13-foot-diameter, which in turn lead to a powerhouse containing five generating units with a total installed capacity of 38,800 kilowatts (kW). Project power is transmitted to the regional grid by six 350-foot-long transmission lines. The power canal, penstocks, and powerhouse bypass a reach of the Mohawk River that is over 4,500 feet long and includes Cohoes Falls, a 65-foot natural waterfall.

Project Name School Street
LIHI Certificate Number 63
LIHI Effective and
Expiration Dates
November 20, 2014
November 20, 2019
Owner Erie Boulevard Hydro, L.P.
State New York
Location Located on the Mohawk river in Albany and Saratoga Counties, New York.
Installed Capacity 38,800 kW
Average Annual Generation 188,500 MWh
Facility Type Run-of-river
FERC No. 2539

The School Street Project dam was constructed in 1831. Electric power generation commenced in 1916, and additional generating units were added in 1922 and 1925. The 16-foot-high dam, located about 4,000 feet above Cohoes Falls, impounds a 100 acre reservoir. Water is diverted at the dam to a power canal, through which it is conveyed to a powerhouse just below Cohoes Falls, and then is returned to the Mohawk River. The FERC issued an original license for the project to Niagara Mohawk on June 11, 1969, with a term expiring on December 31, 1993. The licensing process for the School Street plant has spanned many years. Niagara Mohawk, one of the previous owners of the plant, originally applied for a new license back in 1991. Green Island Power Authority (“GIPA”) did not seek to intervene in the process until 2004, which FERC later ruled was too late.

GIPA, which operates a seven-megawatt hydro plant in the Village of Green Island, has been trying for years to build a 100-megawatt hydro plant on the Mohawk River, just above the historic falls. Those plans were dealt a serious blow two years ago when the Federal Energy Regulatory Commission (“FERC”) granted, Brookfield Renewable Energy, a 40-year license on the School Street Project which is located at the bottom of the falls. During the relicensing process, GIPA had been trying to get FERC to consider its own plan, which has an estimated price tag of $75 million, as an alternative to the Brookfield plant. The August 2009 decision by the U.S. Court of Appeals for the Second Circuit overturned FERC’s 2007 order granting Brookfield a new license. The court sent the case back to the Commission to reconsider, arguing that the FERC “abused its discretion” by shutting GIPA out of the process.

Since the 2009 court decision, the Applicant who has already spent millions of dollars building new park areas with views and historical interpretations of the Cohoes Falls said it is moving forward with plans to expand the School Street Project as part of the requirements of its FERC license. Brookfield has also dredged a power canal that diverts water around the falls to the powerhouse.

Certification History

June 6, 2016: LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board, has certified that the School Street Hydroelectric Project (FERC No. P-2539) satisfies the LIHI Certification Criteria. A Preliminary Certification Decision was announced on May 3, 2016, and a 30-day appeal period was open through June 3, 2016. No requests for appeal were received. This Certification Decision includes two facility-specific conditions, as follows:

  • Condition 1. The facility owner shall provide LIHI with the results of the 2015 downstream bypass efficiency testing for juvenile blueback herring and continue consultation the USFWS Mr. Michael Sale and NYDEC for the purpose of obtaining an updated assessment of the current fish passage effectiveness for that species at the facility. The result of Agency assessments may be: (a) that appropriate passage is being provided at the Project, (b) that effective fish passage effectiveness has not been demonstrated, or (c) that a recent decision has been made that passage at the site for juvenile herring is not needed, thus modifying the original commitments established in the Settlement Agreement and associated agency recommendations. If the 2015 testing is not found to be sufficiently effective and that downstream passage at the site is still required, then the owner shall inform LIHI of their plans to improve operations and continue testing. LIHI strongly recommends that all future testing be coordinated with the agencies to ensure they can participate in the testing. The results of the agency assessment of the 2015 studies shall be provided to LIHI within 60 days of their receipt by the Owner. Additional letters of correspondence from consultation with the USFWS and NYDEC on these passage issues shall also be provided to LIHI within 60 days of receipt by the licensee. LIHI reserves the right to suspend its certification if the agencies do not determine that safe passage is being provided and that such passage needs have not been waived.
  • Condition 2. If a decision is made to pursue installation of the sixth, fish-friendly generating unit at the Project within the next five years, the facility owner shall notify LIHI within 60 days of when FERC approves such an installation. Such installation may lead to a re-evaluation of potentially affected criteria, such as fish passage requirements.

The effective certification date for the School Street Project is November 20, 2014 for a five (5) year term, which will expire on November 20, 2019.

January 7, 2015: LIHI received a comment letter on the application for a second term from the United States Fish and Wildlife Service.  To read the letter, click HERE or scroll to the bottom of the page.

November 19, 2014: On October 21, the Low Impact Hydropower Institute (LIHI) received an application for a second term of Low Impact Certification of the School Street Hydroelectric Project, FERC #2539, located on the Mohawk River in New York. The current Certificate term was scheduled to expire on November 20, 2014, but LIHI has granted a short term extension on the current certificate term to allow for administrative review of the application.  The certificate term has been extended through January 31, 2014.

The 2014 School Street application materials are available below.

November 29, 2010: The School Street Hydroelectric Project has been certified as low impact for a five year term, effective November 20, 2009 and expiring November 20, 2014.

March 4, 2010: LIHI received comments on the School Street Project certification application from Frances Francis, Speigel & McDiarmid.

February 21, 2010: LIHI received comments on the School Street Project application from the Friends of the Falls.

February 12, 2010: LIHI received responses to comments from Brookfield Renewable Power.

January 24, 2010: LIHI responded to Frances Francis’ January 14th letter on behalf of Green Island Power Authority (GIPA). The letter also extends the public comment period to February 26, 2010.

January 22, 2010: LIHI received comments on the School Street Project application from the City of Cohoes.

January 16, 2010: LIHI received comments via email on the School Street Project application from Walter Lipka.

January 14, 2010: LIHI received comments on this application from Frances E. Francis, Spiegel & McDiarmid, LLP on behalf of Green Island Power Authority (GIPA), consisting of a letter to LIHI and a copy of the August 10, 2009 decision of the US Court of Appeals.

November 20, 2009: Erie Boulevard Hydro, L.P. has submitted an application for the certification of the School Street Hydroelectric Project. The public comment period will remain open for 60 days.

All comment letters can be found in the “Files” section at the bottom of the page.


Files: