Harrington Park, New Jersey (August 5, 2016) – LIHI Executive Director Michael J. Sale, using authority delegated from the LIHI Governing Board, has issued a Preliminary Certification Decision that the Medway Hydroelectric Project (FERC No. P-2666) satisfies the LIHI Certification Criteria.  This Preliminary Certification Decision includes one facility-specific condition, as follows:

Condition 1.  The Owner shall be proactive in contacting the MIFWS a minimum of 30 days prior to any planned drawdown of the impoundment that would expose a significant portion of the river bottom, to determine if any special measures are needed to avoid or minimize adverse impacts to state-threatened mussels that may be in the impoundment. The Owner shall work with the MIFWS to implement appropriate mitigation measures should they be needed.  The Owner shall advise LIHI of any such events, including the results of any activities conducted to minimize such impacts. Such notification shall be provided as part of the annual compliance statement to LIHI.

As provided for in Section 4.2.5 of the LIHI 2nd Edition, the Preliminary Certification Decision to certify, along with the Application Reviewer’s report and (if prepared) report of the Executive Director, will be posted on the Institute’s Web page for 30 days.  Notice of the posting will be provided to all individuals or organizations that commented on the initial Application Package.

Any Commenter may submit a letter to the Executive Director requesting an appeal within the 30-day period.  The appeal request must state specific reasons why the hydropower facility should have failed one or more criteria.  If an individual or organization did not comment on the initial Application Package, they may not file an appeal.  Further information about the LIHI appeal process is available in the LIHI Handbook, available at http://lowimpacthydro.org/certification-program-html/.

If no appeal is requested within the 30-day period, the Executive Director will issue LIHI Certification for the facility and post a notification of certification on the Institute’s website.  Once final, the effective certification date for the Medway Project is June 1, 2015 for a five (5) year term, which will expire on June 1, 2020.